BLD11-00450
| FIRE-Final Inspection | 10/18/2011 | 10/18/2011 | 10/18/2011 3:43:07 PM | P | CANC |
|
|
Brian Phone #: ###-####
|
FIR11-00477
| INSP-Final Inspection | 10/17/2011 | 10/18/2011 | 10/18/2011 3:18:48 PM | P | PASS |
|
|
Permit finaled
|
FIR11-00378
| INSP-Final Inspection | 10/17/2011 | 10/18/2011 | 10/18/2011 3:11:59 PM | P | CANC |
|
|
Troy, Please let me know an approximate time, so I can let everyone know. Jason ###-#### Phone #: ###-#### >> Inspection requested via web by Jason Minnick Inspection cancelled from web by: Jason Minnick
|
BLD10-02870
| FIRE-Final Inspection | 10/18/2011 | 10/18/2011 | 10/18/2011 2:50:32 PM | P | PASS |
|
|
Life safety passed.
|
BLD11-00836
| FIRE-Conference | 10/18/2011 | 10/18/2011 | 10/18/2011 2:48:54 PM | P | DONE |
|
|
I stopped today at Bishop Kelly High School to verify that the "dog house", with heat, had been installed over the sprinkler supply piping. It has not. The piping has been wrapped with concrete blankets which I remember was not an option. The openings along the existing wall are covered with plastic but no heat for the space has been provided.
|
FIR11-00299
| INSP-Conference | 10/18/2011 | 10/18/2011 | 10/18/2011 2:48:27 PM | P | DONE |
|
|
I stopped today at Bishop Kelly High School to verify that the "dog house", with heat, had been installed over the sprinkler supply piping. It has not. The piping has been wrapped with concrete blankets which I remember was not an option. The openings along the existing wall are covered with plastic but no heat for the space has been provided.
|
BLD11-01872
| FIRE-Final Inspection | 10/18/2011 | 10/18/2011 | 10/18/2011 2:20:32 PM | P | PASS |
|
|
Life safety passed. The contractor will have the address and apartment numbers posted prior to the building sign off.
|
FIR11-00428
| INSP-Alarm Testing | 10/18/2011 | 10/18/2011 | 10/18/2011 11:33:37 AM | A | DONE |
|
|
Todays inspection was a walk throught to verify device placement prior to actual testing. I found two strobes that are overspaced that will need to be relocated or have the candella increased. Also there is an existing manual pull station that is mounted above 48". I need verification that it met the code under which it was installed or it needs to be lowered.
|
BLD11-01890
| FIRE-Final Inspection | 10/18/2011 | 10/18/2011 | 10/18/2011 11:29:44 AM | P | PASS |
|
|
life safety passed
|
BLD11-01675
| FIRE-Final Inspection | 10/18/2011 | 10/18/2011 | 10/18/2011 11:29:22 AM | P | PASS |
|
|
life safety passed
|
BLD11-00450
| FIRE-Final Inspection | 10/17/2011 | 10/18/2011 | 10/18/2011 10:11:57 AM | A | FAIL |
|
|
Repair the three non-functioning exit signs as marked on the city approved plans.
|
BLD11-02050
| FIRE-Conference | 10/17/2011 | 10/18/2011 | 10/18/2011 10:10:02 AM | A | DONE |
|
|
Went over life safety issues with the superintendant
|
FIR11-00477
| INSP-Sprinkler Rough-in/Hydro | 10/17/2011 | 10/18/2011 | 10/17/2011 10:47:37 AM | P | CANC |
|
|
please contact Jeremy at ###-#### Phone #: ###-#### >> Inspection requested via web by David Dilley Inspection cancelled from web by: David Dilley
|