BLD13-02187
| FIRE-Final Inspection | 10/18/2013 | 10/18/2013 | 10/18/2013 3:53:14 PM | P | CANC |
|
|
Not ready for a final the contractor needed a cover inspection for the fire sprinklers
|
FIR13-00493
| INSP-Final Inspection | 10/18/2013 | 10/18/2013 | 10/18/2013 3:51:39 PM | P | FAIL |
|
|
Need the pendant head in the Dressing Room relocated as previously discussed.
|
BLD13-01918
| FIRE-Final Inspection | 10/18/2013 | 10/18/2013 | 10/18/2013 3:50:10 PM | P | PART |
|
|
With the Buiding Official and Fire Marshals permission a temporary occupancy is being granted with the following condition: An approved fire watch will be posted until the existing fire alarm system is extended into the remodeled space, the two exit signs are installed and tested and emergency lighting is verified and the sprinkler head in the Dressing Room is relocated. Ext 200 or page her-Theresa Taylor Phone #: ###-####
|
FIR13-00537
| INSP-Sprinkler Rough-in | 10/18/2013 | 10/18/2013 | 10/18/2013 3:34:07 PM | P | PASS |
|
|
Sprinkler piping is ok to cover.
|
FIR13-00456
| INSP-Final Inspection | 10/17/2013 | 10/18/2013 | 10/18/2013 3:33:02 PM | P | CANC |
|
|
System still being installed and not ready for inspection
|
FIR13-00456
| INSP-Final Inspection | 10/17/2013 | 10/18/2013 | 10/18/2013 3:32:15 PM | P | CANC |
|
|
System still being installed and not ready for inspection
|
FIR13-00275
| INSP-Final Inspection | 10/17/2013 | 10/18/2013 | 10/18/2013 3:31:24 PM | P | CANC |
|
|
System still being installed and not ready for inspection
|
FIR13-00238
| INSP-Final Inspection | 10/17/2013 | 10/18/2013 | 10/18/2013 3:30:33 PM | P | PASS |
|
|
permit finaled
|
FIR13-00238
| INSP-Final Inspection | 10/17/2013 | 10/18/2013 | 10/18/2013 3:29:28 PM | P | PASS |
|
|
permit finaled
|
FIR13-00238
| INSP-Final Inspection | 10/17/2013 | 10/18/2013 | 10/18/2013 3:22:31 PM | P | PASS |
|
|
Permit finaled. Smoke detector in the basement/facp installed per NFPA 72.7.3.1.4
|
FIR13-00442
| INSP-Final Inspection | 10/17/2013 | 10/18/2013 | 10/18/2013 3:20:47 PM | A | CANC |
|
|
rescheduled for next tuesday
|
BLD12-00452
| FIRE-Final Inspection | 10/17/2013 | 10/18/2013 | 10/18/2013 10:12:37 AM | A | CANC |
|
|
I spoke to Doug about the need to speak to the Building Official to modify the existing fire sprinkler upgrade agreement and getting a final inspection for the project related underground fire sprinkler permit prior to a fire life safety sign off.
|
BLD13-02820
| FIRE-Final Inspection | 10/17/2013 | 10/18/2013 | 10/18/2013 9:21:13 AM | A | PASS |
|
|
life safety passed
|
FIR13-00499
| INSP-Final Inspection | 10/17/2013 | 10/18/2013 | 10/18/2013 8:43:41 AM | A | PASS |
|
|
Permit finaled
|
BLD13-02662
| FIRE-Final Inspection | 10/17/2013 | 10/18/2013 | 10/18/2013 8:26:24 AM | A | PASS |
|
|
life safety passed
|