ELE17-02786
| Final | 10/16/2017 | 10/18/2017 | 10/18/2017 2:34:21 PM | P | PASS |
|
|
We are requesting a final inspection for Wednesday Oct. 18th in the afternoon. Our contact is Rich @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate...room perimeter done...printer not showing up till december, contractor supplying power only, wires safed off and disconnect locked out...ok to final
|
ELE17-03521
| Temporary Service | 10/18/2017 | 10/18/2017 | 10/18/2017 1:32:56 PM | P | PASS |
|
|
temp pole Phone #: ###-#### Inspection requested via web by cal crosby...t/s u/g new ok
|
ELE17-03115
| Electrical Rough-In | 10/18/2017 | 10/18/2017 | 10/18/2017 1:01:28 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton...ceiling grid ok to cover
|
ELE17-02674
| Final | 10/18/2017 | 10/18/2017 | 10/18/2017 12:21:35 PM | P | PASS |
|
|
Please contact Jerry Hardy at ###-#### for property access Phone #: ###-#### Inspection requested via web by jamie berg...ok to final
|
ELE17-01747
| Final | 10/17/2017 | 10/18/2017 | 10/18/2017 11:51:45 AM | P | NR |
|
|
Victor Phone #: ###-####...scheduled for next day PM 10/19/17
|
ELE17-03440
| Final | 10/17/2017 | 10/18/2017 | 10/18/2017 10:40:30 AM | A | PASS |
|
|
Steve Phone #: ###-####...ok to final
|
ELE17-02557
| Final | 10/17/2017 | 10/18/2017 | 10/18/2017 9:50:31 AM | A | PASS |
|
|
It is open. If you have any questions please call Aaron ###-####. Thanks!! Phone #: ###-#### Inspection requested via web by Clay Morgan...corrections made...ok to final
|
ELE17-01458
| Electrical Rough-In | 10/17/2017 | 10/18/2017 | 10/18/2017 9:17:48 AM | A | PASS |
|
|
Inspect 4th floor slab rough in for concrete pour Phone #: ###-#### Inspection requested via web by Jeremy Cloud...ok to pour
|
ELE17-03216
| Final | 10/17/2017 | 10/18/2017 | 10/18/2017 8:46:11 AM | A | PASS |
|
|
Please call Dennis Phone #: ###-#### Inspection requested via web by Kevin Perez... job complete...ok to final
|
ELE17-03216
| Electrical Rough-In | 10/17/2017 | 10/18/2017 | 10/18/2017 8:45:35 AM | A | CANC |
|
|
Please call Dennis Phone #: ###-#### Inspection requested via web by Kevin Perez..
needed perm service as well as rough in
|
ELE17-03216
| Rough-In Permanent Service | 10/18/2017 | 10/18/2017 | 10/18/2017 8:45:07 AM | A | PASS |
|
|
Please call Dennis Phone #: ###-#### Inspection requested via web by Kevin Perez.. rough in ok...underground ok to cover p/s u/g new ok
|
ELE17-03047
| Final | 10/17/2017 | 10/18/2017 | 10/18/2017 8:24:52 AM | A | PASS |
|
|
Call half hour before to meet // Warren Phone #: ###-####...job complete..ok to final
|
ELE17-03047
| Electrical Rough-In | 10/18/2017 | 10/18/2017 | 10/18/2017 8:24:29 AM | A | PASS |
|
|
Call half hour before to meet // Warren Phone #: ###-####...added outlets thu out shop, circuits for mini split systems x 3, exit signs, all surface pipe work...ok
|