Inspections for the day of: Wednesday, October 18, 2017.
Number of inspections: 9
Percentage of inspections complete: 89 %
Percentage of inspections not complete: 11 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR15-00382 INSP-Conference10/11/201710/16/2017 A 
Follow up with Colton
FIR16-00446 INSP-Alarm Testing10/17/201710/18/201710/18/2017 2:10:53 PMPDONE
We set off the alarms and it mistakenly set off the alarms and shunted the elevator in the ajoining building. Testing was stopped and agreed to reschedule for tomorrow morning.

Phone #: ###-#### Inspection requested via web by Stacie Tasker
FIR17-00499 INSP-Sprinkler Rough-in10/18/201710/18/201710/18/2017 2:08:48 PMPPART
See the city approved plans for the two rooms where piping is ok to cover. An additional head is needed in the Storage room as shown on the plans.

Rick Phone #: ###-####
FIR17-00188 INSP-Final Inspection10/17/201710/18/201710/18/2017 2:07:53 PMPPASS
Permit finaled.

Peter Phone #: ###-####
BLD17-03543 FIRE-Final Inspection10/17/201710/18/201710/18/2017 2:07:35 PMAPASS
life safety passed.

Janett Phone #: ###-####
NAF17-00040 INSP-Final10/18/201710/18/201710/18/2017 10:51:45 AMPDONE
life safety passed. the sprinkler system has been removed as per agreement

Call prior to going Phone #: 8018652758 >> Inspection requested via mobile web by Ben johnson
FIR16-00284 INSP-Sprinkler Rough-in/Hydro10/18/201710/18/201710/18/2017 10:01:09 AMPPASS
200 psi Hydro test on dry system passed
BLD17-02385 FIRE-Final Inspection10/17/201710/18/201710/18/2017 8:47:29 AMAFAIL
All items have been corrected except the exit signs and emergency lighting still has issues.
BLD17-02686 FIRE-Final Inspection10/17/201710/18/201710/18/2017 8:46:40 AMAPASS
Life safety passed

Angel Phone #: ###-####