FIR06-00257
| INSP-Sprinkler Rough-in/Hydro | 10/19/2006 | 10/19/2006 | 10/19/2006 5:11:16 PM | P | PART |
|
|
UG fire supply line hydrostatic test passed. UG flush also completed satisfactory post hydro.
|
FIR06-00351
| INSP-Sprinkler Rough-in/Hydro | 10/19/2006 | 10/19/2006 | 10/19/2006 5:08:35 PM | P | FAIL |
|
|
Need approved plans on site for the TI work prior to inspection for cover or rough-in approval.
|
MIS06-00275
| FIR-Final | 10/18/2006 | 10/19/2006 | 10/19/2006 2:41:13 PM | A | FAIL |
|
|
Need to provide a current inspection certification tag for the fire extinguisher, door hardware at the second exit is not approved, must be single motion operable as discussed.
|
BLD06-01921
| FIRE-Final Inspection | 10/19/2006 | 10/19/2006 | 10/19/2006 1:01:27 PM | P | PASS |
|
|
Fire life safety is satisfactory, the provided PFE to be attatched to the new wall when paint is completed per contractor.
|
FIR06-00596
| INSP-Final Inspection | 10/17/2006 | 10/19/2006 | 10/19/2006 12:31:24 PM | A | DEFR |
|
|
Per contractor, inspection to be rescheduled for 10/20 as discussed.
|
FIR06-00595
| INSP-Alarm Testing | 10/13/2006 | 10/19/2006 | 10/19/2006 12:30:18 PM | A | DEFR |
|
|
Inspection to be performed on 10/20 per agreement.
|
FIR06-00351
| INSP-Sprinkler Rough-in/Hydro | 10/17/2006 | 10/19/2006 | 10/19/2006 12:28:54 PM | A | NR |
|
|
Work is not yet completed for inspection, to be rescheduled for the afternoon.
|
BLD06-00769
| FIRE-Final Inspection | 10/18/2006 | 10/19/2006 | 10/19/2006 10:32:41 AM | A | PART |
|
|
Units 304 thru 307 and unit 312 are okay for life safety final, unit 315 second floor needs primary power supply functional for the smoke alarms-the detectors were functional on battery backup test.
|