ESC15-00971
| BMP Violation | 10/15/2015 | 10/19/2015 | 10/20/2015 4:09:07 PM | P | PASS |
|
|
Corrections complete. Site is now back in compliance. Street and sidewalk have been swept and the DI bag on corner of Kimball and Woodland has been installed.
|
ESC14-01019
| Aging Inspection | 10/19/2015 | 10/19/2015 | 10/20/2015 9:17:14 AM | | PASS |
|
|
|
ESC15-00556
| Random Inspection | 10/19/2015 | 10/19/2015 | 10/19/2015 5:29:38 PM | P | FAIL |
|
|
Post precipitation inspection conducted at 4 PM Singificant sediment runoff from disturbed areas in EV phase 1 & 2, in particular at the northeast corner along HV Road as well rill erosion through banks and slopes in
No BMPS installed or implemented at site other than DI protection, resulting in sediment running off site with a storm rated at 0.10 - 0.25" in last 24 hours of inspection. With more rainfall and intensity situation would be much worse.
Corrections: 1. Meeting on site to discuss BMP installation 2. Clean roads, 3. No corrections or response has been made on the CN issued 10/14, other than notification work would resume. 4. Need to apply hydroseed and/or hydromulch slopes not actively being worked up. 5. No SWPPP signage or information found on site.
|
ESC13-00443
| Aging Inspection | 10/19/2015 | 10/19/2015 | 10/19/2015 4:36:12 PM | | PASS |
|
|
No activity, no active BLD permit for vacant. Temp BMP perimeter control wattles installed, no sediment leaving site and no trackout. Materials have been removed from site and stockpile graded & spread across lot.
|
ESC14-00403
| Aging Inspection | 10/19/2015 | 10/19/2015 | 10/19/2015 4:32:42 PM | | CANC |
|
|
|
ESC15-01222
| Site Preparation | 10/19/2015 | 10/19/2015 | 10/19/2015 3:41:49 PM | P | PASS |
|
|
Clint Phone #: ###-####
Site is ready for construction. Subdivision BMPs (DI sediment protection, concrete washouts) are installed and being utilized. No trackout, dust issues, or windblown trash issues from active Tahoe sites in DH#12 at this time. Approved.
|
ESC15-01253
| Site Preparation | 10/19/2015 | 10/19/2015 | 10/19/2015 3:32:59 PM | P | PASS |
|
|
Clint Phone #: ###-####
Clint Phone #: ###-####
First set of 4 DH Estates on corner of Perrault and Parkcenter. Permit sign posted. RP in process of finalizing preparations.
1. Cement washout to be installed on open parcel next to projects. 2. 2.x DI bags need to be installed in alley way where access and driveways will be.
BMPs should be installed tomorrow, approved to start initial excavation. Test pits reveal ground water at approximately 10-12 feet at this time.
|
ESC15-01252
| Site Preparation | 10/19/2015 | 10/19/2015 | 10/19/2015 3:32:44 PM | P | PASS |
|
|
Clint Phone #: ###-####
Clint Phone #: ###-####
First set of 4 DH Estates on corner of Perrault and Parkcenter. Permit sign posted. RP in process of finalizing preparations.
1. Cement washout to be installed on open parcel next to projects. 2. 2.x DI bags need to be installed in alley way where access and driveways will be.
BMPs should be installed tomorrow, approved to start initial excavation. Test pits reveal ground water at approximately 10-12 feet at this time.
|
ESC15-01251
| Site Preparation | 10/19/2015 | 10/19/2015 | 10/19/2015 3:32:29 PM | P | PART |
|
|
Clint Phone #: ###-####
Clint Phone #: ###-####
First set of 4 DH Estates on corner of Perrault and Parkcenter. Permit sign posted. RP in process of finalizing preparations.
1. Cement washout to be installed on open parcel next to projects. 2. 2.x DI bags need to be installed in alley way where access and driveways will be.
BMPs should be installed tomorrow, approved to start initial excavation. Test pits reveal ground water at approximately 10-12 feet at this time.
|
ESC15-01250
| Site Preparation | 10/19/2015 | 10/19/2015 | 10/19/2015 3:32:03 PM | P | PART |
|
|
Clint Phone #: ###-####
First set of 4 DH Estates on corner of Perrault and Parkcenter. Permit sign posted. RP in process of finalizing preparations.
1. Cement washout to be installed on open parcel next to projects. 2. 2.x DI bags need to be installed in alley way where access and driveways will be.
BMPs should be installed tomorrow, approved to start initial excavation. Test pits reveal ground water at approximately 10-12 feet at this time.
|
ESC14-01042
| Aging Inspection | 10/19/2015 | 10/19/2015 | 10/19/2015 2:42:53 PM | | CANC |
|
|
|