Inspections for the day of: Monday, October 19, 2015.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-00971 BMP Violation10/15/201510/19/201510/20/2015 4:09:07 PMPPASS
Corrections complete. Site is now back in compliance. Street and sidewalk have been swept and the DI bag on corner of Kimball and Woodland has been installed.
ESC14-01019 Aging Inspection10/19/201510/19/201510/20/2015 9:17:14 AM PASS
ESC15-00556 Random Inspection10/19/201510/19/201510/19/2015 5:29:38 PMPFAIL
Post precipitation inspection conducted at 4 PM Singificant sediment runoff from disturbed areas in EV phase 1 & 2, in particular at the northeast corner along HV Road as well rill erosion through banks and slopes in

No BMPS installed or implemented at site other than DI protection, resulting in sediment running off site with a storm rated at 0.10 - 0.25" in last 24 hours of inspection. With more rainfall and intensity situation would be much worse.

Corrections:
1. Meeting on site to discuss BMP installation
2. Clean roads,
3. No corrections or response has been made on the CN issued 10/14, other than notification work would resume.
4. Need to apply hydroseed and/or hydromulch slopes not actively being worked up.
5. No SWPPP signage or information found on site.
ESC13-00443 Aging Inspection10/19/201510/19/201510/19/2015 4:36:12 PM PASS
No activity, no active BLD permit for vacant. Temp BMP perimeter control wattles installed, no sediment leaving site and no trackout. Materials have been removed from site and stockpile graded & spread across lot.
ESC14-00403 Aging Inspection10/19/201510/19/201510/19/2015 4:32:42 PM CANC
ESC15-01222 Site Preparation10/19/201510/19/201510/19/2015 3:41:49 PMPPASS
Clint Phone #: ###-####

Site is ready for construction. Subdivision BMPs (DI sediment protection, concrete washouts) are installed and being utilized. No trackout, dust issues, or windblown trash issues from active Tahoe sites in DH#12 at this time. Approved.
ESC15-01253 Site Preparation10/19/201510/19/201510/19/2015 3:32:59 PMPPASS
Clint Phone #: ###-####

Clint Phone #: ###-####

First set of 4 DH Estates on corner of Perrault and Parkcenter. Permit sign posted. RP in process of finalizing preparations.

1. Cement washout to be installed on open parcel next to projects.
2. 2.x DI bags need to be installed in alley way where access and driveways will be.

BMPs should be installed tomorrow, approved to start initial excavation. Test pits reveal ground water at approximately 10-12 feet at this time.
ESC15-01252 Site Preparation10/19/201510/19/201510/19/2015 3:32:44 PMPPASS
Clint Phone #: ###-####

Clint Phone #: ###-####

First set of 4 DH Estates on corner of Perrault and Parkcenter. Permit sign posted. RP in process of finalizing preparations.

1. Cement washout to be installed on open parcel next to projects.
2. 2.x DI bags need to be installed in alley way where access and driveways will be.

BMPs should be installed tomorrow, approved to start initial excavation. Test pits reveal ground water at approximately 10-12 feet at this time.
ESC15-01251 Site Preparation10/19/201510/19/201510/19/2015 3:32:29 PMPPART
Clint Phone #: ###-####

Clint Phone #: ###-####

First set of 4 DH Estates on corner of Perrault and Parkcenter. Permit sign posted. RP in process of finalizing preparations.

1. Cement washout to be installed on open parcel next to projects.
2. 2.x DI bags need to be installed in alley way where access and driveways will be.

BMPs should be installed tomorrow, approved to start initial excavation. Test pits reveal ground water at approximately 10-12 feet at this time.
ESC15-01250 Site Preparation10/19/201510/19/201510/19/2015 3:32:03 PMPPART
Clint Phone #: ###-####

First set of 4 DH Estates on corner of Perrault and Parkcenter. Permit sign posted. RP in process of finalizing preparations.

1. Cement washout to be installed on open parcel next to projects.
2. 2.x DI bags need to be installed in alley way where access and driveways will be.

BMPs should be installed tomorrow, approved to start initial excavation. Test pits reveal ground water at approximately 10-12 feet at this time.
ESC14-01042 Aging Inspection10/19/201510/19/201510/19/2015 2:42:53 PM CANC