Inspections for the day of: Wednesday, October 19, 2016.
Number of inspections: 22
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD16-03756 FIRE-Final Inspection10/19/201610/19/201610/19/2016 2:47:25 PMPPASS
Life safety passed
BLD16-00840 FIRE-Final Inspection10/18/201610/19/201610/19/2016 2:10:24 PMAPASS
Life safety passed
BLD16-00839 FIRE-Final Inspection10/18/201610/19/201610/19/2016 2:02:32 PMAPASS
Life safety passed
BLD16-00838 FIRE-Final Inspection10/18/201610/19/201610/19/2016 2:01:38 PMAPASS
Life safety passed
BLD16-00198 FIRE-Final Inspection10/18/201610/19/201610/19/2016 2:00:49 PMAPASS
Life safety passed
BLD16-00837 FIRE-Final Inspection10/18/201610/19/201610/19/2016 1:56:36 PMAPASS
Life safety passed
BLD16-00847 FIRE-Final Inspection10/18/201610/19/201610/19/2016 1:53:46 PMAPASS
Life safety passed
BLD16-00846 FIRE-Final Inspection10/18/201610/19/201610/19/2016 1:50:58 PMAPASS
Life safety passed
BLD16-00845 FIRE-Final Inspection10/18/201610/19/201610/19/2016 1:50:36 PMAPASS
Life safety passed
BLD16-00844 FIRE-Final Inspection10/18/201610/19/201610/19/2016 1:50:02 PMAPASS
Life safety passed
BLD16-00843 FIRE-Final Inspection10/18/201610/19/201610/19/2016 1:49:19 PMAPASS
Life safety passed
BLD16-00842 FIRE-Final Inspection10/18/201610/19/201610/19/2016 1:48:27 PMAPASS
Life safety passed
BLD16-00841 FIRE-Final Inspection10/18/201610/19/201610/19/2016 1:47:59 PMAPASS
Life safety passed
BLD16-03742 FIRE-Final Inspection10/19/201610/19/201610/19/2016 1:41:16 PMPPASS
life safety passed
BLD06-02310 FIRE-Final Inspection10/18/201610/19/201610/19/2016 10:47:44 AMAPASS
Life safety passed. Fire hydrant has been installed. No sprinkler or alarm requirements per the review notes. Inspection was for the shell/core only.
BLD06-02311 FIRE-Final Inspection10/18/201610/19/201610/19/2016 10:47:20 AMAPASS
Life safety passed. Fire hydrant has been installed. No sprinkler or alarm requirements per the review notes. Inspection was for the shell/core only.
BLD15-04521 FIRE-Final Inspection10/18/201610/19/201610/19/2016 9:25:36 AMAPART
A temporary for fire life safety is ok with Scotts permission until ADA single action hardware is provided for the mezzanine Server Room, first floor Restrooms and the doors that separate the Showroom from the Warehouse.
FIR16-00658 INSP-Sprinkler Rough-in10/18/201610/19/201610/19/2016 9:13:52 AMAPASS
The underground supply piping is ok to cover
FIR16-00654 INSP-Final Inspection10/18/201610/19/201610/19/2016 9:12:10 AMAPASS
permit finaled
BLD16-00733 FIRE-Final Inspection10/18/201610/19/201610/19/2016 8:55:31 AMAPASS
Life safety passed
FIR16-00659 INSP-Sprinkler Rough-in10/18/201610/19/201610/19/2016 8:45:34 AMAPASS
Underground supply piping is ok for cover
FIR16-00645 INSP-Sprinkler Rough-in10/18/201610/19/201610/19/2016 8:45:07 AMAPART
Underground piping is ok to cover. Concrete for thrust blocks not on site until afternoon and will verify ok to cover for thrust blocks then.