BLD16-01472
| FIRE-Final Inspection | 10/19/2016 | 10/19/2016 | 10/19/2016 3:03:21 PM | P | PASS |
|
|
Final fire sprinkler inspection complete, final fire alarm inspection complete, fire extinguishers are in common area's with current inspection tags (Fire extinguisher inspection tags will expire at the end of October) Final life fire safety inspection passed/complete.
|
FIR16-00531
| INSP-Final Inspection | 10/19/2016 | 10/19/2016 | 10/19/2016 3:00:10 PM | P | PASS |
|
|
Final fire sprinkler inspection passed/complete
|
FIR16-00625
| INSP-Final Inspection | 10/19/2016 | 10/19/2016 | 10/19/2016 2:59:46 PM | P | PASS |
|
|
Final fire alarm inspection passed/complete
|
FIR16-00625
| INSP-Alarm Testing | 10/18/2016 | 10/19/2016 | 10/19/2016 2:58:59 PM | P | DONE |
|
|
Fire alarm testing complete
|
FIR16-00645
| INSP-Sprinkler Rough-in | 10/19/2016 | 10/19/2016 | 10/19/2016 2:03:42 PM | P | PASS |
|
|
Rough to cover inspection for underground supply complete, underground supply approved for cover.
|
FIR16-00661
| INSP-Sprinkler Rough-in | 10/19/2016 | 10/19/2016 | 10/19/2016 11:55:36 AM | P | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, overhead fire sprinkler piping located in area of work approved for cover.
|
FIR16-00101
| INSP-Sprinkler Rough-in | 10/18/2016 | 10/19/2016 | 10/19/2016 11:39:31 AM | P | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping/tenting located above northwest stairwell and northwest hotel room on level 5 complete, overhead fire sprinkler piping located in noted area's approved for cover.
|
BLD16-02004
| FIRE-Final Inspection | 10/19/2016 | 10/19/2016 | 10/19/2016 11:36:41 AM | P | PASS |
|
|
Final fire sprinkler inspection complete, no fire alarm modifications, commercial hood suppression system has a current inspection tag, fire extinguishers will be mounted in discussed locations. Final life fire safety inspection passed/complete.
|
FIR15-00427
| INSP-Final Inspection | 10/19/2016 | 10/19/2016 | 10/19/2016 10:56:23 AM | P | PASS |
|
|
Final fire sprinkler inspection passed/complete.
|
FIR16-00639
| INSP-Sprinkler Rough-in/Hydro | 10/18/2016 | 10/19/2016 | 10/19/2016 9:55:53 AM | A | PART |
|
|
Rough to cover inspection for overhead fire sprinkler piping located above hardlids complete. Overhead fire sprinkler piping located above hardlids in area of work approved for cover.
|