Inspections for the day of: Thursday, October 19, 2017.
Number of inspections: 9
Percentage of inspections complete: 89 %
Percentage of inspections not complete: 11 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR15-00382 INSP-Conference10/11/201710/16/2017 A 
Follow up with Colton
BLD17-00617 FIRE-Final Inspection10/19/201710/19/201710/19/2017 2:14:35 PMAPASS
Life safety passed

Phone #: ###-#### Inspection requested via web by kevin debelloy
FIR17-00555 INSP-Final Inspection10/18/201710/19/201710/19/2017 1:56:18 PMPFAIL
Provide 24 hour back up power as per the review comments for the internet form of communication, relocate the smoke detector to be above the facp, provide the shield wire between the AES and facp, remove the horn/strobe from the lobby, provide as-builts showing the two low air and to water flow switches, provide functional testing of the two low air and two water flow switches, provide document box, provide updated map

Peter - new fire alarm panel Phone #: ###-####
BLD17-00525 FIRE-Final Inspection10/18/201710/19/201710/19/2017 11:11:46 AMAPASS
Life safety passed.

Matthew Phone #: ###-####
BLD17-03582 FIRE-Final Inspection10/18/201710/19/201710/19/2017 8:58:10 AMAPASS
Life safety passed

Bridgette Phone #: ###-####
FIR16-00284 INSP-Sprinkler Rough-in/Hydro10/18/201710/19/201710/19/2017 8:49:23 AMADONE
24 hour air test on dry system started at 8:45 with 44psi on the guage.
FIR16-00446 INSP-Alarm Testing10/18/201710/19/201710/19/2017 8:38:28 AMADONE
For todays inspection I witnessed the corrections for the notification devices and verified sync. and that all notification devices were functional. No initiating devices have been tested. Not all access has been provided for the fire/smoke dampers and not all of the fire sprinkler devices have been connected and pre-tested yet.
FIR17-00570 INSP-Final Inspection10/18/201710/19/201710/19/2017 8:36:23 AMAFAIL
Strobe modifications are needed due to the new mechanical closet blocking coverage.
FIR17-00539 INSP-Final Inspection10/18/201710/19/201710/19/2017 8:35:33 AMAPASS
Permit finaled