Inspections for the day of: Friday, October 2, 2009.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00482 INSP-Sprinkler Rough-in/Hydro10/1/200910/2/200910/2/2009 3:20:35 PMPPART
Todays inspection completed the first floor high area which is ok to cover but the piping addition will need to be shown on the resubmittals. I also inspected the basement which will need to be resubmitted due to changes and overspaced pendants. The pendants have been calculated for 121 square feet per head but many exceed that. I gave the ok to cover on the piping over the offices along the north basement wall but head spacing will have to conform to the resubmitted plans when approved. The underground pipe type and size does not match approved plans. I asked Trent to please reflect the changes on the resubmittals.
FIR09-00582 INSP-Final Inspection10/2/200910/2/200910/2/2009 3:16:46 PMPPASS
Permit finaled. One extended coverage pendant did not meet the four times rule for a column obstruction but Don had it relocated at my second trip to the job site.
FIR09-00589 INSP-Final Inspection10/2/200910/2/200910/2/2009 2:48:05 PMPPASS
Permit finaled. One existing a/v is overspaced in exiting area and will remain that way until a remodel. One existing 15cd strobe in an existing corridor with a new wall wsa changed, while I waited, to a 110cd strobe. EOL drop was verified on this circuit.
BLD09-00946 FIRE-Conference10/1/200910/2/200910/2/2009 12:51:29 PMADONE
Per conversation between Darren with HC Company, Mark Sentenno and myself areas of this project will be phased. The tenant will be able to occupy the remodeled areas as long as all fire alarm, fire sprinkler and fire life safety items are complete in the occupied remodeled areas. A final will be given when the entire project is complete.
BLD09-00945 FIRE-Conference10/1/200910/2/200910/2/2009 12:51:05 PMADONE
Per conversation between Darren with HC Company, Mark Sentenno and myself areas of this project will be phased. The tenant will be able to occupy the remodeled areas as long as all fire alarm, fire sprinkler and fire life safety items are complete in the occupied remodeled areas. A final will be given when the entire project is complete.
FIR08-00094 INSP-Final Inspection10/1/200910/2/200910/2/2009 11:57:29 AMAPASS
Permit finaled
BLD09-01536 FIRE-Final Inspection10/1/200910/2/200910/2/2009 10:19:39 AMAPASS
Life safety passed.
BLD09-00489 FIRE-Final Inspection10/1/200910/2/200910/2/2009 8:43:35 AMAPASS
Life safety passed.
FIR09-00482 INSP-Sprinkler Rough-in/Hydro10/1/200910/2/200910/1/2009 4:05:56 PMACANC
Please call 15 min prior to insppection Phone #: ###-#### Internet Inspection Request from: Trent Bice Inspection cancelled from web by: Trent Bice