PLM99-03297
| Final | 10/19/1999 | 10/20/1999 | 10/20/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 10/19/1999 at 13:37:03. Contact: ###-####.
|
PLM99-03561
| Final | 10/19/1999 | 10/20/1999 | 10/20/1999 12:00:00 AM | A | FAIL |
|
|
agustin--- ###-#### backflow insp--call 1st before insp RP required
|
PLM99-01475
| Final | 10/19/1999 | 10/20/1999 | 10/20/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 10/19/1999 at 16:11:14. Contact: ###-####.
|
PLM99-02750
| Final | 10/19/1999 | 10/20/1999 | 10/20/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 10/19/1999 at 16:17:26. Contact: ###-####. lock box 0853
|
PLM99-03520
| Plumbing Rough-in | 10/20/1999 | 10/20/1999 | 10/20/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 10/20/1999 at 08:04:43. Contact: ###-####.
|
PLM99-03564
| Sprinkler (Final) | 10/20/1999 | 10/20/1999 | 10/20/1999 12:00:00 AM | P | PASS |
|
|
Don Roth ###-####
|
PLM99-03167
| Final | 10/20/1999 | 10/20/1999 | 10/20/1999 12:00:00 AM | P | PASS |
|
|
###-#### SHOULD BE OPEN OR KEY IN A/C DISCONNECT BOX
|
PLM99-03566
| Plumbing Rough-in | 10/20/1999 | 10/20/1999 | 10/20/1999 12:00:00 AM | P | PASS |
|
|
NELS ###-####
|
PLM99-03567
| Sprinkler (Final) | 10/20/1999 | 10/20/1999 | 10/20/1999 12:00:00 AM | P | PASS |
|
|
SPRINKLER KEN ###-####
|
PLM99-02220
| Plumbing Rough-in | 10/20/1999 | 10/20/1999 | 10/20/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 10/20/1999 at 10:10:21. Contact: ###-####. R/I and roof drains
|
PLM99-03571
| Final | 10/20/1999 | 10/20/1999 | 10/20/1999 12:00:00 AM | P | PASS |
|
|
w/s only scott ###-####
|
PLM99-03573
| Final | 10/20/1999 | 10/20/1999 | 10/20/1999 12:00:00 AM | P | CANC |
|
|
w/s only ###-#### SHOULD BE WATER/SEWER
|
PLM99-03573
| Water and/or Sewer | 10/20/1999 | 10/20/1999 | 10/20/1999 12:00:00 AM | P | PASS |
|
|
###-####FINAL
|