ELE00-02235
| Final | 10/19/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 10/19/2000 at 22:44:43. Contact: ###-####. completed. 10/20/2000 11:34:21 AM
|
ELE00-02235
| Final | 10/19/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 10/19/2000 at 22:44:43. Contact: ###-####. completed. 10/20/2000 11:34:21 AM
|
ELE00-04058
| Temporary Service | 10/19/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | A | PART |
|
|
ron ###-#### t/p. 10/20/2000 11:33:28 AM
|
ELE00-04058
| Temporary Service | 10/19/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | A | PART |
|
|
ron ###-#### t/p. 10/20/2000 11:33:28 AM
|
ELE98-03567
| Electrical Rough-In | 10/19/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 10/19/2000 at 13:42:28. Contact: ###-####. p.v.c. groundwork; parking lot lighting. 10/20/2000 11:31:58 AM
|
ELE98-03567
| Electrical Rough-In | 10/19/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 10/19/2000 at 13:42:28. Contact: ###-####. p.v.c. groundwork; parking lot lighting. 10/20/2000 11:31:58 AM
|
ELE00-03603
| Final | 10/19/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | P | PASS |
|
|
Kelly ###-####. completed. 10/20/2000 9:55:32 PM
|
ELE00-03457
| Final | 10/20/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 10/20/2000 at 08:06:00. Contact: ###-####. corrections completed. 10/20/2000 10:01:42 PM
|
ELE00-03680
| Rough-In Permanent Service | 10/20/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | P | PART |
|
|
jim ###-####. walls ele r/i; service panel not completed. 10/20/2000 9:57:56 PM
|
ELE00-04070
| Electrical Rough-In | 10/20/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | P | PASS |
|
|
r/i ###-#### john --also a panel. dividing wall; sub-panel ele r/i. 10/20/2000 9:59:56 PM
|
ELE00-04071
| Electrical Rough-In | 10/20/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | P | PART |
|
|
divided wall john ###-#### . dividing wall ele r/i. 10/20/2000 9:58:47 PM
|
ELE00-04074
| Permanent Service | 10/20/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | P | PASS |
|
|
Please call Mark first at ###-####. called tenant to have ele contractor connect wires to main breaker at main disconnect. 10/23/2000 11:52:22 AM
|
ELE00-04035
| Final | 10/20/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | P | PASS |
|
|
FN INSP MITCH ###-#### . corrections completed as instructed per jschmer. 10/20/2000 10:05:20 PM
|
ELE00-01971
| Electrical Rough-In | 10/20/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | P | PASS |
|
|
R/I --JIM ###-####. pvc in pad ready for concrete pour. 10/20/2000 10:09:00 PM
|
ELE00-01303
| Electrical Rough-In | 10/20/2000 | 10/20/2000 | 10/20/2000 12:00:00 AM | P | PART |
|
|
ufer ground charles ###-####. ufer ground ok to pour; garage ele r/i, ok. 10/20/2000 10:07:30 PM
|