Inspections for the day of: Wednesday, October 20, 2010.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR10-00326 FIR-Aging Inspection10/20/201010/20/201010/28/2010 10:28:32 AM NR
Work is in progress. Per Guy all of these AES inspections are being called in shortly.
FIR10-00327 FIR-Aging Inspection10/20/201010/20/201010/28/2010 10:27:30 AM NR
Work is in progress. Per Guy all of these AES inspections are being called in shortly.
FIR10-00236 INSP-Sprinkler Rough-in/Hydro10/20/201010/20/201010/20/2010 2:58:23 PMPPASS
The new drops/arm-overs in the lay-in ceiling tile areas are ok to cover. Also the overhead hydro test of the new sprinkler piping passed.
FIR10-00072 INSP-Sprinkler Rough-in/Hydro10/19/201010/20/201010/20/2010 2:05:33 PMAPASS
The under ground hydro passed. No flush was performed.
BLD10-02422 FIRE-Final Inspection10/20/201010/20/201010/20/2010 1:12:25 PMPPASS
life safety passed