ESC14-00950
| Site Preparation | 10/20/2014 | 10/20/2014 | 10/20/2014 3:49:53 PM | P | PASS |
|
|
phone requested by Tony ###-####
Site is ready for excavation. Permit and BMPs are in place. Approved.
|
ESC14-00951
| Site Preparation | 10/20/2014 | 10/20/2014 | 10/20/2014 3:47:50 PM | P | PASS |
|
|
Tony ###-####
Permit posted. East Valley BMPs in place. Lined concrete washout is provided. Advised Tony to have them stake down the lining better
Approved.
|
ESC14-00144
| General Inspection | 10/20/2014 | 10/20/2014 | 10/20/2014 3:45:27 PM | | PASS |
|
|
East Valley subdivision now has individual homes being built. No major trackout, discharges, dust or other issues observed. Fiber wattles have been installed in areas where sediment ran off lots in the last storm event and all stormdrain DI's have filter protection. No corrections at this time.
|
ESC13-00230
| General Inspection | 10/20/2014 | 10/20/2014 | 10/20/2014 3:12:03 PM | | PASS |
|
|
Riverheights #5 has about 65% of the lots filled. Open area is being used for landscaping staging and some stockpiles. There is a construction entrance into this area. Lined concrete washout is installed and has remaining capacity. All stormdrain inlets have filter bag protection. No trackout or other violations. Approved.
|
ESC14-00909
| Site Preparation | 10/20/2014 | 10/20/2014 | 10/20/2014 3:08:44 PM | P | PASS |
|
|
Permit posted . River Heights and Brighton Homes project currently in good standing. Approved to begin excavation when ready.
|
ESC14-00212
| General Inspection | 10/20/2014 | 10/20/2014 | 10/20/2014 2:02:03 PM | | PASS |
|
|
Vertical construction is in progress at Lusk Place. Dewatering and diversion of seepage water is still occuring. RP Jose Bautista has a log of turbidity readings. The discharge appeared very clear with no other dectectable water quality issues. Runs into Ann Morisson ponds and stream channels. Jose stated that dewatering is occuring due to utility work to be performed by United Water on Lusk Street.
Permit is posted on trailers as well as SWPPP, wattles protect north side of site, minimal trackout. Site is in compliance with ESC condtions.
|
ESC12-00130
| General Inspection | 10/20/2014 | 10/20/2014 | 10/20/2014 1:25:33 PM | | PASS |
|
|
Apartment complex vertical construction in progress. Crew on site pouring asphalt on utility trench on Royal. No discharges, spills, or significant amount of sediment on street.
Construction is installed to reduce trackout, rear silt fence along river side is trenched in and next to fencing. Permit posted. SWPPP on site.
Approved.
|
ESC14-00175
| General Inspection | 10/20/2014 | 10/20/2014 | 10/20/2014 1:17:57 PM | | PASS |
|
|
Permit posted on construction fencing. Parking lot is paved and private stormdrains are protected. No stockpiles or disturbed areas outside construction area. No trackout to Roosevelt or Kootenai. No violations observed. WIP
|
ESC13-00513
| Aging Inspection | 10/20/2014 | 10/20/2014 | 10/20/2014 12:00:41 PM | | PASS |
|
|
Finaled.
|
ESC13-00513
| DOC - Permit Finaled | 10/20/2014 | 10/20/2014 | 10/20/2014 12:00:27 PM | P | PASS |
|
|
No construction activity or disturbed area at site. No outstanding ESC violations. No activity on BLD permit in over 1 year. Permit expired. No further ESC inspections.
|
ESC13-00490
| Random Inspection | 10/20/2014 | 10/20/2014 | 10/20/2014 11:54:08 AM | A | PASS |
|
|
WIP at Jackson's remodel/addition. DI on Roosevelt has filter bag protection. No trackout and a lined concrete washout is on site. Permit posted. No violations observed.
|
ESC14-00200
| General Inspection | 10/20/2014 | 10/20/2014 | 10/20/2014 11:29:50 AM | | PART |
|
|
Entrance to Involta is now paved eliminating trackout issues. Crew onsite installing landscaping and irrigation lines. Exterior fram is built with work remaing on the interior. No dust or nonstormwater discharges observed.
Crew installing fence posts is not using a designated washout and has washed out in a few seperate places along fence line. Berm to the east of building is tracked vertically which could cause rill erosion is not regraded/stabilized.
Two verbal corrections to RP Bernie 1. Make fence crew use designated lined washout. 2. Retrack berm or provide schedule for stabilization.
|
ESC14-00656
| General Inspection | 10/17/2014 | 10/20/2014 | 10/20/2014 10:53:41 AM | A | PASS |
|
|
Site has combination of silt fence and construction fencing to establish a perimeter control and control access. Permit is posted, construction entrance is a paved surface. Surrounding stormdrain inlets at carwash at business building have sediment protection. MS4 on Overland as well. No trackout, dust, or uncontained trash observed. Approved.
|
ESC13-01159
| General Inspection | 10/17/2014 | 10/20/2014 | 10/20/2014 10:44:28 AM | A | PASS |
|
|
Peppermill Estates' individual lots have not yet started construction. Streets, gutters, and utilities are complete. Some work is ongoing for common area fencing, landscaping and stormwater ponds/swales at front of site.
No trackout or erosion of sediment occuring on parcels. Permit and SWPPP information is posted. No discharges or chemical storage at site.
Approved. No corrections at this time.
|
ESC14-00567
| General Inspection | 10/17/2014 | 10/20/2014 | 10/20/2014 10:03:08 AM | A | PASS |
|
|
Warehouse demo & new addition is in progress. No disturbed area or loosed sediment on front of building on Westpark. Permit is posted with contact info. The rear parking lot to the south has had some trench work that is not yet patched over so there is some loose sediment. The grassy swale inlet has sandbag to collect dirt. No trackout. Will be swept after paving.
Site is in compliance with permit conditions.
|
ESC14-00818
| Site Preparation | 10/17/2014 | 10/20/2014 | 10/20/2014 9:06:11 AM | A | NR |
|
|
Kevin Phone #: ###-####
Crew has not yet installed ESC controls; contractor Kevin will re-schedule site prep inspection when ready. No excavation yet.
|
ESC13-00259
| Aging Inspection | 10/20/2014 | 10/20/2014 | 10/20/2014 8:57:48 AM | | PASS |
|
|
Triplett Sub development phase is complete. Townhomes are in progress, upper view lots are vegetated. Rocky swale drainage is protected by well established grass and silt fence between the swale and the area of disturbance. Tahoe Homes is using a lined concrete washout pit.
No corrections at this time. Will keep permit open through completion of townhomes.
|