FIR15-00403
| INSP-Sprinkler Rough-in/Hydro | 10/20/2015 | 10/20/2015 | 10/20/2015 4:11:44 PM | P | PASS |
|
|
Rough to cover inspection for underground passed/complete, approved for cover
|
FIR15-00402
| INSP-Sprinkler Rough-in/Hydro | 10/20/2015 | 10/20/2015 | 10/20/2015 4:11:15 PM | P | PASS |
|
|
Rough to cover inspection for underground passed/complete, approved for cover
|
FIR15-00400
| INSP-Sprinkler Rough-in/Hydro | 10/20/2015 | 10/20/2015 | 10/20/2015 4:10:20 PM | P | PASS |
|
|
Rough to cover inspection for underground passed/complete, approved for cover
|
FIR15-00408
| INSP-Sprinkler Rough-in | 10/20/2015 | 10/20/2015 | 10/20/2015 2:09:34 PM | P | PASS |
|
|
Last area inspected for rough to cover, all area's of project approved for cover.
|
BLD15-03319
| FIRE-Final Inspection | 10/19/2015 | 10/20/2015 | 10/20/2015 11:31:21 AM | A | PASS |
|
|
Life fire safety passed/complete
|
BLD15-03301
| FIRE-Final Inspection | 10/19/2015 | 10/20/2015 | 10/20/2015 11:30:50 AM | A | PASS |
|
|
Life fire safety passed/complete
|
BLD15-03318
| FIRE-Final Inspection | 10/19/2015 | 10/20/2015 | 10/20/2015 11:30:11 AM | A | PASS |
|
|
Life fire safety passed/complete
|