MEC09-02531
| Rough-in | 10/21/2009 | 10/21/2009 | 10/21/2009 3:17:36 PM | P | PASS |
|
|
Please complete a rough-in inspection as well as a gas pressure test. Call eric ###-#### with any questions Phone #: ###-#### Internet Inspection Request from: Alana Lane
|
MEC09-02531
| Pressure Test | 10/21/2009 | 10/21/2009 | 10/21/2009 3:17:15 PM | P | PASS |
|
|
Please complete a rough-in inspection as well as a gas pressure test. Call eric ###-#### with any questions Phone #: ###-#### Internet Inspection Request from: Alana Lane 20#
|
MEC09-02582
| Final | 10/20/2009 | 10/21/2009 | 10/21/2009 3:05:27 PM | P | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: April Sims
|
ESC09-00331
| Random Inspection | 10/21/2009 | 10/21/2009 | 10/21/2009 3:05:04 PM | P | PASS |
|
|
site ok
|
MEC09-02343
| Final | 10/19/2009 | 10/21/2009 | 10/21/2009 2:30:11 PM | P | PASS |
|
|
Please call homeowner, Roberta, at ###-#### prior to inspection. Thank you. Phone #: ###-#### Internet Inspection Request from: bryan taylor
|
MEC08-01298
| Final | 10/21/2009 | 10/21/2009 | 10/21/2009 1:45:20 PM | P | FAIL |
|
|
Sorry Troy no luck, please expire this permit. Thanks! Phone #: ###-#### Internet Inspection Request from: April Sims unable to complete inspection, homeowner will not respond to contractor
|
MEC08-01298
| DOC - Permit Expired | 10/21/2009 | 10/21/2009 | 10/21/2009 1:44:00 PM | P | PASS |
|
|
Sorry Troy no luck, please expire this permit. Thanks! Phone #: ###-#### Internet Inspection Request from: April Sims contractor unable to make contact with homeowner for final inspection
|
MIS09-00201
| MEC-Conference | 10/21/2009 | 10/21/2009 | 10/21/2009 1:42:39 PM | P | DONE |
|
|
received mechanical value of $15,924 by GC for work performed under this Building permit number Bld08-01433 scope of work, but no mechanical permit attached or created for this project. Please meet with Carrier Corp. about which permit this work was pulled under and if combined with another project we need to split out the permits. Carrier Corp # is ###-####, and I have not talked to them yet about this....thanks Tisha
|
MIS09-00201
| MEC-Final | 10/21/2009 | 10/21/2009 | 10/21/2009 1:42:30 PM | P | PASS |
|
|
received mechanical value of $15,924 by GC for work performed under this Building permit number Bld08-01433 scope of work, but no mechanical permit attached or created for this project. Please meet with Carrier Corp. about which permit this work was pulled under and if combined with another project we need to split out the permits. Carrier Corp # is ###-####, and I have not talked to them yet about this....thanks Tisha talked with Carrier and work performed for this project was for controls only
|
MIS09-00200
| MEC-Conference | 10/21/2009 | 10/21/2009 | 10/21/2009 1:41:28 PM | P | DONE |
|
|
received mechanical value of $30,070 by GC for work performed under this Building permit number Bld08-01271 scope of work, but no mechanical permit attached or created for this project. Please meet with Carrier Corp. about which permit this work was pulled under and if combined with another project we need to split out the permits. Carrier Corp # is ###-####, and I have not talked to them yet about this....thanks Tisha
|
MIS09-00200
| MEC-Final | 10/21/2009 | 10/21/2009 | 10/21/2009 1:41:18 PM | P | PASS |
|
|
received mechanical value of $30,070 by GC for work performed under this Building permit number Bld08-01271 scope of work, but no mechanical permit attached or created for this project. Please meet with Carrier Corp. about which permit this work was pulled under and if combined with another project we need to split out the permits. Carrier Corp # is ###-####, and I have not talked to them yet about this....thanks Tisha talked with Carrier and work performed for this phase was for controls only
|
MEC09-02023
| Pressure Test | 10/20/2009 | 10/21/2009 | 10/21/2009 11:33:24 AM | A | FAIL |
|
|
Phone #: ###-#### Internet Inspection Request from: Michele LaMott no test, ubable to do inspection gas pipe covered
|
MEC09-02023
| Rough-in | 10/20/2009 | 10/21/2009 | 10/21/2009 11:32:31 AM | A | FAIL |
|
|
Phone #: ###-#### Internet Inspection Request from: Michele LaMott no rough inspection done, job is already sheetrocked, talked to mike with tml to have someone meet me there
|
MEC08-01665
| Final | 10/20/2009 | 10/21/2009 | 10/21/2009 10:32:50 AM | A | PASS |
|
|
call Greg with any questions Phone #: ###-#### Internet Inspection Request from: Greg Mendiola
|
MEC09-02290
| Final | 10/21/2009 | 10/21/2009 | 10/21/2009 10:04:32 AM | A | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Veronica Shipley
|
MEC09-02290
| Pressure Test | 10/21/2009 | 10/21/2009 | 10/21/2009 10:04:00 AM | A | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Veronica Shipley
|
MEC08-02947
| Final | 10/20/2009 | 10/21/2009 | 10/21/2009 9:26:59 AM | A | PASS |
|
|
Internet Inspection Request from: Greg Mendiola
|
MEC09-02527
| Final | 10/20/2009 | 10/21/2009 | 10/21/2009 8:39:41 AM | A | PASS |
|
|
Side door to garage will be open. You can access through gate next to garage and enter. Thank you. Phone #: ###-#### Internet Inspection Request from: bryan taylor
|