Inspections for the day of: Wednesday, October 22, 1997.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorCarl Dependahl
TitleBLD-COM/RES INSPECTOR
Phone #794-9492
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD96-02800 INSP - Foundation10/21/199710/22/199710/22/1997 12:00:00 AMAPART
GROUT REPORT FOR 10/21/97 12 YDS INTERIOR AND EXTERIOR WALLS MTI ONSITE, PENDING REPORT.
BLD96-03200 INSP - Conference10/22/199710/22/199710/22/1997 12:00:00 AMAPASS
W/ STEED (ODIE)...NEED INSTALL 1HR AT SPRINKLER RM & CALL FOR INSP FOR FINAL.
BLD97-00411 INSP - Final10/22/199710/22/199710/22/1997 12:00:00 AMPFAIL
NEED PLBG & ELEC; STRUCT C/N
BLD97-01323 INSP - Conference10/23/199710/22/199710/22/1997 12:00:00 AMPPASS
W CONT & 408 RE FINAL REQS
BLD97-01699 INSP - Final10/22/199710/22/199710/22/1997 12:00:00 AMPFAIL
KEY ABOVE FRONT DOOOR...C/N, AIR SEAL, VAPOR BARRIER, HTG FINAL, ROOF PENETRATION
BLD97-02351 INSP - Conference10/23/199710/22/199710/22/1997 12:00:00 AMPPASS
MET W/ PAUL LOMBARDI AT SITE RE C/N & POSSIBLE FIXES, NEED CLARIFY TRUSS BRG & BEAMS....REMOVE BEAM W/ FLAWS AT BAY WINDOW.
BLD97-02351 INSP - Energy code compliance10/22/199710/22/199710/22/1997 12:00:00 AMPFAIL
NEED ADD HI R AT GAR...INS AT TALL WALLS ON EXT & V.B. AT EXT.
BLD97-02351 INSP - Framing/Rough-in10/22/199710/22/199710/22/1997 12:00:00 AMPFAIL
C/N. NEED VERIFY TRUSS BRG & BEAM ADEQUACY. NEEED PERMIT TO FINISH BONUS RM. ADD INSUL & VAPOR BARRIER AS REQ'D.
BLD96-02800 INSP - Carpentry10/22/199710/22/199710/22/1997 12:00:00 AMPPASS
W/ SUPT. & HOBSON. 2:30; CHK'D PLAN DETAIL, DAMPER LISTINGS & INSTALL INSTRUCTION...MET W/ BILL OF HOBSON FABRICATORS.