FIR19-00747
| INSP-Sprinkler Rough-in | 10/22/2019 | 10/22/2019 | 10/22/2019 3:07:31 PM | P | PASS |
|
|
Rough-in approved.
Approved plans are on site. There are no new ceilings being installed, this rough in is to make sure everything looks good before we schedule a final. Please call Matt before heading to the site at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
BLD18-03122
| FIRE-Final Inspection | 10/22/2019 | 10/22/2019 | 10/22/2019 2:49:25 PM | P | PASS |
|
|
Life safety passed.
Matt Phone #: ###-####
|
BLD18-02497
| FIRE-Final Inspection | 10/22/2019 | 10/22/2019 | 10/22/2019 2:00:27 PM | P | PART |
|
|
A temp for life safety is being given with boise fire approval. Need a permit for the solar panel/system and one additional exit discharge light is needed at the south east exit door.
Ken Phone #: ###-####
|
FIR19-00544
| INSP-Sprinkler Rough-in | 10/21/2019 | 10/22/2019 | 10/22/2019 1:51:57 PM | P | PASS |
|
|
Rough-in passed for the remaining piping. Piping can be covered. One pendant head still needs to be added in the small closet.
Contact Noemi Carrero ###-#### 30 min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
FIR19-00704
| INSP-Final Inspection | 10/22/2019 | 10/22/2019 | 10/22/2019 1:07:13 PM | P | PASS |
|
|
Rough-in passed. Piping ok for cover.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
BLD18-04449
| FIRE-Final Inspection | 10/21/2019 | 10/22/2019 | 10/22/2019 12:36:58 PM | A | PASS |
|
|
Life safety passed,.
Michael Phone #: ###-####
|
FIR19-00221
| INSP-Sprinkler Rough-in | 10/21/2019 | 10/22/2019 | 10/22/2019 12:15:45 PM | A | PASS |
|
|
See the city approved plans for an additional apartment on the first floor south building where soffit piping is ok for cover. Tom Phone #: ###-####
|
BLD17-02262
| FIRE-Final Inspection | 10/22/2019 | 10/22/2019 | 10/22/2019 11:36:14 AM | P | PASS |
|
|
Life safety passed.
Tony Phone #: ###-####
|
BLD17-02261
| FIRE-Final Inspection | 10/22/2019 | 10/22/2019 | 10/22/2019 11:35:29 AM | P | PASS |
|
|
Life safety passed.
Tony Phone #: ###-####
|
FIR19-00531
| INSP-Sprinkler Rough-in/Hydro | 10/21/2019 | 10/22/2019 | 10/22/2019 10:39:13 AM | A | PASS |
|
|
The underground hydro test was witnessed with no visible pressure loss.
Matt Phone #: ###-####
|
FIR19-00365
| INSP-Sprinkler Rough-in | 10/21/2019 | 10/22/2019 | 10/22/2019 10:30:04 AM | A | PASS |
|
|
Rough-in for piping and hangers passed for the north wing. See the city approved plans for location. Another rough to cover inspection will be required when the drops have been installed . I noted acouple of missing upright heads and possible blocked heads due to truss webbing. I went over the "three time rule" with fitter.
|
BLD19-00771
| FIRE-Final Inspection | 10/21/2019 | 10/22/2019 | 10/22/2019 10:20:44 AM | A | PART |
|
|
Temp for life safety until the project related fire alarm permit is finaled. eciso Phone #: ###-####
|
FIR19-00355
| INSP-Final Inspection | 10/21/2019 | 10/22/2019 | 10/22/2019 10:20:04 AM | A | PART |
|
|
A temp for fire alarm with boise fire approval until a notification device is added in the Reading Room. These are engineered plans and will need their approval prior to submittal to the city.
possibly 7am // Brandon Phone #: ###-####
|
FIR19-00359
| INSP-Final Inspection | 10/21/2019 | 10/22/2019 | 10/22/2019 10:00:17 AM | A | PASS |
|
|
Permit finaled
Contact Ken Orahood ###-#### 30 Min prior to Final Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|