ELE17-03379
| Final | 10/22/2019 | 10/22/2019 | 10/22/2019 3:14:56 PM | P | PASS |
|
|
Job complete, Final ok
|
ELE19-02902
| Electrical Rough-In | 10/21/2019 | 10/22/2019 | 10/22/2019 11:07:32 AM | A | PASS |
|
|
trench out front only Phone #: ###-#### Inspection requested via web by David McClellan R/I ok cover trench to post light
|
ELE19-01739
| Electrical Rough-In | 10/21/2019 | 10/22/2019 | 10/22/2019 11:06:54 AM | A | PASS |
|
|
trench only Phone #: ###-#### Inspection requested via web by David McClellan Depth of trench to post light verifed r/i ok cover
|
ELE19-03503
| Electrical Rough-In | 10/21/2019 | 10/22/2019 | 10/22/2019 10:59:55 AM | A | FAIL |
|
|
fireplace is in. other corrections done Phone #: ###-#### Inspection requested via web by David McClellan Original corrections completed, Building code requires smoke/carbon detectors install outside sleeping areas
|
ELE19-03739
| Electrical Rough-In | 10/21/2019 | 10/22/2019 | 10/22/2019 10:17:17 AM | A | PASS |
|
|
underground inspection. please call Jeff with questions Phone #: ###-#### Inspection requested via web by A.M.E. Office Rough-in ok cover trenching exterior of structure, 3 locations
|