FIR14-00565
| INSP-Supply line flush | 10/23/2014 | 10/23/2014 | 10/23/2014 5:14:19 PM | P | PART |
|
|
UG fire supply line flush completed satisfactory.
|
FIR14-00571
| INSP-Final Inspection | 10/23/2014 | 10/23/2014 | 10/23/2014 3:55:06 PM | P | PASS |
|
|
Previous correction items verified for completion. Fire sprinkler permit finaled. Walkthrough passed.
|
FIR14-00605
| INSP-Final Inspection | 10/23/2014 | 10/23/2014 | 10/23/2014 2:46:11 PM | P | FAIL |
|
|
Completed initial walkthrough and testing of occupant notification. Items noted include; non-functional speaker at the audit room, audibility not met at the SW conference room, need to verify operations under fire alarm condition at both delayed egress doors when powered, need to verify two DH and WON door operability without bypass enabled.
|
BLD14-03075
| FIRE-Final Inspection | 10/23/2014 | 10/23/2014 | 10/23/2014 2:31:30 PM | P | FAIL |
|
|
Need to provide approved style hardware at the main entry/exit. Install single motion, fail safe hardware or provide a keyed deadbolt and signage per plan review red-lines.
|
FIR14-00604
| INSP-Sprinkler Rough-in | 10/22/2014 | 10/23/2014 | 10/23/2014 2:29:00 PM | A | PART |
|
|
Completed rough-in at building area B 2nd floor. Items noted include; possible light fixture obstructions at unit 201 master closet, field modifications to install at units 201 and 207, overspaced sprinkler at unit 206 bedroom, elevator lobby, mech., data, trash and hskpg rooms are not yet piped, 2" main and tie-ins at the coridor are finished. Unit 206 spacing redone while on site. Additional plan sheets for inspection purposes to match approved set and be provided with the city stamp.
|
FIR14-00742
| INSP-Sprinkler Rough-in | 10/22/2014 | 10/23/2014 | 10/23/2014 11:18:52 AM | A | PART |
|
|
Okay to cover overhead fire sprinkler work at the remodel area.
|