PLM96-01265
| INSP - Final | 10/23/1996 | 10/24/1996 | 10/24/1996 12:00:00 AM | A | PART |
|
|
10/24/96 330 - LATE AM UNIT 206 206 final ok, 10/22/96 103 final ok
|
PLM96-02925
| INSP - Plumbing Rough-in | 10/23/1996 | 10/24/1996 | 10/24/1996 12:00:00 AM | A | PASS |
|
|
10/24/96 330 - done yesterday
|
PLM96-03190
| INSP - Sewer line | 10/23/1996 | 10/24/1996 | 10/24/1996 12:00:00 AM | A | PASS |
|
|
10/24/96 330 - replacing sewer line to house
|
PLM96-03191
| INSP - Plumbing Rough-in | 10/23/1996 | 10/24/1996 | 10/24/1996 12:00:00 AM | A | NR |
|
|
10/24/96 330 -
|
PLM96-03191
| INSP - Plumbing Rough-in | 10/24/1996 | 10/24/1996 | 10/24/1996 12:00:00 AM | P | PART |
|
|
10/24/96 330 - this is a duplacate
|
PLM96-03193
| INSP - Plumbing Rough-in | 10/23/1996 | 10/24/1996 | 10/24/1996 12:00:00 AM | P | FAIL |
|
|
10/24/96 330 - not ready, no test vents not thru roof etc
|
PLM96-03204
| INSP - Sprinkler & Backflow | 10/24/1996 | 10/24/1996 | 10/24/1996 12:00:00 AM | P | PASS |
|
|
10/24/96 330 -
|
PLM96-03206
| INSP - Sewer and Water lines | 10/24/1996 | 10/24/1996 | 10/24/1996 12:00:00 AM | P | PASS |
|
|
10/24/96 330 -
|
PLM96-03209
| INSP - Plumbing Rough-in | 10/24/1996 | 10/24/1996 | 10/24/1996 12:00:00 AM | P | PASS |
|
|
10/24/96 330 - r/i ok with co at upper terminal
|
PLM96-03191
| INSP - Plumbing Rough-in | 10/24/1996 | 10/24/1996 | 10/24/1996 12:00:00 AM | P | FAIL |
|
|
10/24/96 330 - REINSPECTION provide R-13 at master tub valve
|
PLM96-02376
| INSP - Sewer line | 10/24/1996 | 10/24/1996 | 10/24/1996 12:00:00 AM | P | PART |
|
|
10/24/96 330 - PARTIAL 3" COOLING TOWER DRAIN AT N2 PLANT
|
PLM96-02499
| INSP - Water lines | 10/24/1996 | 10/24/1996 | 10/24/1996 12:00:00 AM | P | PART |
|
|
10/24/96 330 - PARTIAL WATER RELOCATION AND SERVICE SEPERATION AT 17C GR FIRE LINE
|