Inspections for the day of: Monday, October 24, 2005.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00076 INSP-Alarm Testing10/24/200510/24/200510/24/2005 4:45:45 PMAPART
Partial shell alarm inspection only.
FIR05-00075 INSP-Alarm Testing10/24/200510/24/200510/24/2005 4:44:24 PMAFAIL
Need to retest elevator lobby smoke detectors as they have been connected and reconnected for ceiling tile installation, need to test elevator heat detector in pit, provide sign at FACP room, no knox box provided yet, need audibility in the FACP room as discussed.
FIR05-00426 INSP-Alarm Testing10/24/200510/24/200510/24/2005 4:36:21 PMAFAIL
Provide resubmittals for changes( added strobe, 180cd strobes at outside seating area, moved 75cd strobe in the kitchen) some duct smoke detectors are mounted incorrectly.
FIR05-00459 INSP-Alarm Testing10/24/200510/24/200510/24/2005 4:32:07 PMPCANC
No time available for this inspection today.
FIR05-00559 INSP-Final Inspection10/21/200510/24/200510/24/2005 4:30:52 PMPFAIL
Orientation and length of the sample tubes in the ductwork are not correctly installed, activation of the duct smoke detector produced a weak intermittent alarm signal reading 4.5 at the EOL under battery power.
BLD05-01993 FIRE-Final Inspection10/24/200510/24/200510/24/2005 3:36:29 PMPCANC
No time available for this inspection today, spoke with contractor to reschedule for tomorrow am.
BLD05-02218 BLD-Framing/Rough-in10/21/200510/24/200510/24/2005 3:33:33 PMACANC
Wrong inspection type called in, notified contractor at ###-####.
BLD04-01323 FIRE-Final Inspection10/21/200510/24/200510/24/2005 3:08:39 PMPFAIL
A 12 item correction list was discussed and left with Gary of Devcon construction for the shell permit life safety.
FIR05-00089 INSP-Sprinkler Rough-in/Hydro10/21/200510/24/200510/24/2005 3:06:31 PMAFAIL
A 13 item correction list was discussed and left with Brian of DeBest sprinkler for the shell rough-in.
FIR05-00520 INSP-Final Inspection10/24/200510/24/200510/24/2005 12:00:00 AMPCANC
Scheduled by a contractor via Hello! on 10/24/2005 at 7:58:44 AM. Contact: ###-####. canc kirk
FIR05-00531 INSP-Alarm Testing10/24/200510/24/200510/24/2005 12:00:00 AMPCANC
Scheduled by a contractor via Hello! on 10/24/2005 at 8:01:03 AM. Contact: ###-####. cancel