FIR14-00667
| INSP-Sprinkler Rough-in | 10/23/2014 | 10/24/2014 | 10/27/2014 10:14:01 AM | A | PASS |
|
|
Rough-in passed. Piping can be covered as marked on the approved plans. This includes doghouses.
|
BLD14-01391
| FIRE-Final Inspection | 10/24/2014 | 10/24/2014 | 10/24/2014 2:28:18 PM | P | PASS |
|
|
life safety passed
|
FIR14-00657
| INSP-Final Inspection | 10/24/2014 | 10/24/2014 | 10/24/2014 1:09:30 PM | P | CANC |
|
|
Anytime afternoon is ok Phone #: ###-#### Inspection requested via web by Matt Casey
|
FIR14-00418
| INSP-Sprinkler Rough-in/Hydro | 10/24/2014 | 10/24/2014 | 10/24/2014 1:09:14 PM | P | PASS |
|
|
Overhead hydro test passed
|
FIR14-00419
| INSP-Sprinkler Rough-in/Hydro | 10/24/2014 | 10/24/2014 | 10/24/2014 1:08:53 PM | P | PASS |
|
|
Overhead hydro test passed
|
BLD14-02358
| FIRE-Final Inspection | 10/24/2014 | 10/24/2014 | 10/24/2014 1:06:12 PM | P | PASS |
|
|
Life safety passed
|
FIR14-00417
| INSP-Sprinkler Rough-in/Hydro | 10/24/2014 | 10/24/2014 | 10/24/2014 12:44:40 PM | P | PASS |
|
|
Ovehead hydro test passed.
|
FIR14-00416
| INSP-Final Inspection | 10/24/2014 | 10/24/2014 | 10/24/2014 12:40:29 PM | P | PASS |
|
|
Permit finaled
|
FIR14-00644
| INSP-Final Inspection | 10/24/2014 | 10/24/2014 | 10/24/2014 12:38:12 PM | P | PASS |
|
|
Permit finaled
|
FIR14-00581
| INSP-Sprinkler Rough-in | 10/24/2014 | 10/24/2014 | 10/24/2014 10:22:22 AM | P | PASS |
|
|
The north and south stairwell insulation is complete and can be covered. The second floor insulation is complete and piping can be covered.
|
BLD14-02509
| FIRE-Final Inspection | 10/24/2014 | 10/24/2014 | 10/24/2014 10:09:16 AM | P | PASS |
|
|
Life safety passed
|
BLD14-01391
| FIRE-Final Inspection | 10/23/2014 | 10/24/2014 | 10/24/2014 10:07:50 AM | A | FAIL |
|
|
Repair the east door exit sign.
|
FIR14-00667
| INSP-Sprinkler Rough-in | 10/23/2014 | 10/24/2014 | 10/24/2014 9:58:06 AM | A | PASS |
|
|
24 hour air test passed
|
FIR14-00667
| INSP-Sprinkler Rough-in/Hydro | 10/23/2014 | 10/24/2014 | 10/24/2014 9:14:03 AM | A | PASS |
|
|
24 hour air test on dry system passed
|
BLD14-00819
| FIRE-Conference | 10/24/2014 | 10/24/2014 | 10/24/2014 9:11:29 AM | A | PASS |
|
|
North and south stairwell insulation is complete and piping can be covered. Second floor insulation is complete and sprinkler piping can be covered.
|
BLD14-02358
| FIRE-Final Inspection | 10/23/2014 | 10/24/2014 | 10/24/2014 9:05:35 AM | A | FAIL |
|
|
Provide correct occupant load signs and exit discharge lighting as per the approval note number 3. All other items appear ok.
|
FIR14-00647
| INSP-Final Inspection | 10/24/2014 | 10/24/2014 | 10/24/2014 7:10:09 AM | P | CANC |
|
|
Anytime is fine Phone #: ###-#### >> Inspection requested via web by Matt Casey Inspection cancelled from web by: Matt Casey
|