MEC99-03541
| Rough-in | 10/22/1999 | 10/25/1999 | 10/25/1999 12:00:00 AM | A | FAIL |
|
|
janet ###-#### r/I Seal R/h in basement; Dryer vent needs to be 6" due to # of elbows.
|
MEC99-03551
| Final | 10/22/1999 | 10/25/1999 | 10/25/1999 12:00:00 AM | A | PASS |
|
|
dick ###-#### f/p only F/P ok
|
MEC99-02254
| Final | 10/22/1999 | 10/25/1999 | 10/25/1999 12:00:00 AM | A | FAIL |
|
|
n/w heating--- ###-#### fn insp---re-insp Need 18" clearance at F/P termination to combustible in basement per manufacturer; Cut out 2 sides of stand off for air dissipation
|
MEC99-03280
| Final | 10/20/1999 | 10/25/1999 | 10/25/1999 12:00:00 AM | A | PASS |
|
|
SHAWNA ###-#### FN
|
MEC99-03005
| Final | 10/22/1999 | 10/25/1999 | 10/25/1999 12:00:00 AM | P | FAIL |
|
|
MISTY ###-#### Not ready
|
MEC99-03440
| Final | 10/22/1999 | 10/25/1999 | 10/25/1999 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 10/22/1999 at 16:13:27. Contact: ###-####. Not ready
|
MEC99-03497
| Pressure Test | 10/25/1999 | 10/25/1999 | 10/25/1999 12:00:00 AM | P | PASS |
|
|
reinspect ###-#### Gas ok
|
MEC99-03497
| Rough-in | 10/25/1999 | 10/25/1999 | 10/25/1999 12:00:00 AM | P | PASS |
|
|
reinspect randy ###-#### R/I ok
|
MEC99-01823
| Final | 10/25/1999 | 10/25/1999 | 10/25/1999 12:00:00 AM | P | PART |
|
|
Met contractor on site to discuss correction
|
MEC99-03533
| Pressure Test | 10/25/1999 | 10/25/1999 | 10/25/1999 12:00:00 AM | P | PASS |
|
|
Gas ok
|
MEC99-03480
| Rough-in | 10/25/1999 | 10/25/1999 | 10/25/1999 12:00:00 AM | P | PASS |
|
|
per dixie send to her for re-insp on r/I B-vent clearance ok- pass R/I
|
MEC99-03567
| Final | 10/25/1999 | 10/25/1999 | 10/25/1999 12:00:00 AM | P | FAIL |
|
|
David Windom ###-#### Not ready
|