Inspections for the day of: Thursday, October 25, 2007.
Number of inspections: 13
Percentage of inspections complete: 92 %
Percentage of inspections not complete: 8 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00694 INSP-Conference10/19/200710/22/2007 A 
PIV issue
FIR07-00525 INSP-Final Inspection10/23/200710/25/200710/26/2007 4:24:05 PMPFAIL
See approved plans 1st floor for areas in need of repair including three SD to be relocated, strobes are not in sync at the pool room, fireman's hat needs to illuminate solid upon activation of the SD at the elevator lobby, need to test EOL, provide signals report at next inspection, noted corrections have been verified from the previous inspection.
FIR06-00007 INSP-Final Inspection10/23/200710/25/200710/25/2007 5:21:22 PMADEFR
Scheduled for 10/26
FIR07-00305 INSP-Final Inspection10/24/200710/25/200710/25/2007 3:08:33 PMANR
Project is not in condition for final approval, also need to coordinate inspection with the sprinkler contractor, discussed project schedule.
FIR07-00441 INSP-Final Inspection10/25/200710/25/200710/25/2007 2:19:45 PMPNH
No access available to the areas in need of inspection.
BLD06-02598 FIRE-Final Inspection10/24/200710/25/200710/25/2007 2:17:53 PMPFAIL
Provide building address numbers, remove the manual thumbturn at the door from the SW office, provide signage at the door the to fire riser room.
FIR07-00716 INSP-Final Inspection10/25/200710/25/200710/25/2007 12:15:43 PMPFAIL
Still missing field ceiling tiles at several locations.
FIR07-00812 INSP-Sprinkler Rough-in10/24/200710/25/200710/25/2007 11:44:35 AMAPART
UG fire supply line installation per scope of work is acceptable pending satisfactory compliance with Boise City Fire Prevention Code adoption 7-01-46. The fire service line must be dedicated single use for the overhead fire sprinkler system or be looped if accomodating both hydrants and OH supply. Notified contractor of the situation. Per Jim Danes of American Fire the line is planned for future looped connection, date uncertain. Per the civil drawings, the UG fire service line is shown as single use for OH fire protection only.
FIR07-00360 FIR-Aging Inspection10/25/200710/25/200710/25/2007 11:30:55 AM DEFR
Work in progress.
FIR07-00364 INSP-Final Inspection10/25/200710/25/200710/25/2007 11:01:36 AMPPASS
UG fire supply line permit finaled.
FIR06-00562 INSP-Final Inspection10/24/200710/25/200710/25/2007 10:34:26 AMAPASS
Final inspection passed per K. Roule, fire alarm permit finaled.
BLD07-01744 FIRE-Final Inspection10/24/200710/25/200710/25/2007 10:31:40 AMANR
EM lights and exit signs are not ready.
FIR07-00765 INSP-Final Inspection10/24/200710/25/200710/25/2007 10:29:51 AMAPASS
Fire sprinkler passed final inspection, permit finaled.