BLD98-01484
| INSP-Conference | 10/26/1998 | 10/26/1998 | 10/26/1998 12:00:00 AM | A | PART |
|
|
profit for partial opening on 11/13. gave requirements to contractor
|
BLD98-01052
| INSP-Conference | 10/26/1998 | 10/26/1998 | 10/26/1998 12:00:00 AM | A | PART |
|
|
profit meeting for partial opening scheduled for 11/13 - gave requirements to contractor
|
BLD98-01122
| INSP-Final Inspection | 10/23/1998 | 10/26/1998 | 10/26/1998 12:00:00 AM | P | FAIL |
|
|
larry ###-#### retest voice evac; complete 2 hour wall; sprinklers for glazing
|
BLD97-02488
| INSP-Final Inspection | 10/26/1998 | 10/26/1998 | 10/26/1998 12:00:00 AM | P | PASS |
|
|
re-inspection for final occ approved
|
BLD98-02139
| INSP-Final Inspection | 10/23/1998 | 10/26/1998 | 10/26/1998 12:00:00 AM | P | FAIL |
|
|
larry ###-#### sprinkler and extinguisher
|
BLD98-02141
| INSP-Final Inspection | 10/23/1998 | 10/26/1998 | 10/26/1998 12:00:00 AM | P | FAIL |
|
|
larry ###-#### sprinklers and extinguisher
|
BLD98-02928
| INSP-Final Inspection | 10/26/1998 | 10/26/1998 | 10/26/1998 12:00:00 AM | P | FAIL |
|
|
re-inspect for final NAC not supervised
|