ESC12-00403
| General Inspection | 10/26/2016 | 10/26/2016 | 10/28/2016 8:24:17 AM | | CANC |
|
|
|
ESC14-00296
| General Inspection | 10/26/2016 | 10/26/2016 | 10/27/2016 1:01:30 PM | | PEND |
|
|
CCP now open with some work remaining. Need to sweep/clean Capitol sidewalk bricks and remove DI bag on Main Street.
|
ESC15-01175
| General Inspection | 10/26/2016 | 10/26/2016 | 10/27/2016 11:42:33 AM | | PASS |
|
|
No trackout to Myrtle or Capitol. Vertical construction in progress. No discharges or spills observed in staging areas.
|
ESC11-00879
| General Inspection | 10/26/2016 | 10/26/2016 | 10/27/2016 11:22:59 AM | | CANC |
|
|
|
ESC13-00806
| General Inspection | 10/26/2016 | 10/26/2016 | 10/27/2016 11:21:19 AM | | CANC |
|
|
|
ESC15-00403
| General Inspection | 10/26/2016 | 10/26/2016 | 10/27/2016 11:18:44 AM | | PASS |
|
|
WIP on exterior finish and interior. Loose dirt in guttter on Bown has been removed/cleaned. No new trackout or issues.
|
ESC16-00064
| Aging Inspection | 10/26/2016 | 10/26/2016 | 10/27/2016 11:02:17 AM | | PASS |
|
|
WIP. Central area behind units not yet stabilized. BMPs in Park Place installed and no violations observed. Trash contained, no spills or discharges. No trackout. Concrete washhout provided. See also ESC14-01083
|
ESC16-00065
| Aging Inspection | 10/26/2016 | 10/26/2016 | 10/27/2016 11:02:04 AM | | PASS |
|
|
WIP. Central area behind units not yet stabilized. BMPs in Park Place installed and no violations observed. Trash contained, no spills or discharges. No trackout. Concrete washhout provided. See also ESC14-01083
|
ESC16-00063
| Aging Inspection | 10/26/2016 | 10/26/2016 | 10/27/2016 11:01:52 AM | | PASS |
|
|
WIP. Central area behind units not yet stabilized. BMPs in Park Place installed and no violations observed. Trash contained, no spills or discharges. No trackout. Concrete washhout provided. See also ESC14-01083
|
ESC16-00118
| Aging Inspection | 10/26/2016 | 10/26/2016 | 10/27/2016 10:46:47 AM | | PASS |
|
|
landscaping in progress. no violations. near completion. Multiple SFHs on Ghost Bar active. DIs protected. No trackout from open areas.
|
ESC16-00143
| Aging Inspection | 10/26/2016 | 10/26/2016 | 10/27/2016 10:44:07 AM | | PASS |
|
|
Home complete, landscaped and occupied. No loose dirt or other materials. Active projects by Tahoe on HV Rd in compliance.
|
ESC15-01465
| Site Final | 10/25/2016 | 10/26/2016 | 10/27/2016 10:25:11 AM | P | PASS |
|
|
Home complete, lansdcaped, and ready for occupation. Temp BMPs in DHE to remain during active construction. Active projects in compliance.
|
ESC16-01454
| Site Preparation | 10/26/2016 | 10/26/2016 | 10/27/2016 9:46:33 AM | P | PASS |
|
|
Mark Phone #: ###-####-please go before 3 or call Mark and reschedule
Permit sign posted in front window. Frontage and sidewalk to remain undisturbed. Construction access through alley. RP/GC will contain concrete washout on site. Approved.
|
ESC16-00537
| General Inspection | 10/26/2016 | 10/26/2016 | 10/27/2016 9:22:05 AM | | PASS |
|
|
WIP within Veteran's Park. Staging area in parking lot. No violations observed.
|
ESC16-00284
| Site Final | 10/21/2016 | 10/26/2016 | 10/27/2016 9:10:30 AM | A | CANC |
|
|
|
ESC16-01398
| Site Preparation | 10/25/2016 | 10/26/2016 | 10/27/2016 9:09:30 AM | A | PASS |
|
|
Jim Phone #: ###-####
Approved for construction
|
ESC16-00523
| General Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 10:04:38 AM | | PASS |
|
|
WIP on rear equipment yard grading. No trackout. Grade below EoP and stormwater retained onsite
|
ESC16-00649
| Site Preparation | 10/25/2016 | 10/26/2016 | 10/26/2016 9:54:35 AM | A | PART |
|
|
Joel Phone #: ###-####
Subdivision BMPs installed. Permit sign posted. Approved for excavation but CBH RP Colby to address following corrections:
- sweep Abram street gutters - sweep up CBH home on Abram & Sweetwater - install new inlet bag on Abram & Sweetwater (west side)
|
ESC16-00697
| General Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 9:52:29 AM | A | PART |
|
|
WIP on Dropzone Apartments. Construction entrance installed, lined washout provided, permit signs posted.
RP Colby w/ CBH is onsite. No trackout or discharges observed.
Verbal Correction Request: - sweep Abram Street - install new inlet bag on Abram at Sweetwater - replace inlet bags on Fastwaster - lengthen construction entrance to 50 ft
RP stated will install new inlet bags today (x3) and order street sweeper for Thursday or Friday.
|
ESC16-00697
| General Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 9:51:55 AM | A | PART |
|
|
WIP on Dropzone Apartments. Construction entrance installed, lined washout provided, permit signs posted.
RP Colby w/ CBH is onsite. No trackout or discharges observed.
Verbal Correction Request: - sweep Abram Street - install new inlet bag on Abram at Sweetwater - replace inlet bags on Fastwaster - lengthen construction entrance to 50 ft
RP stated will install new inlet bags today (x3) and order street sweeper for Thursday or Friday.
|
ESC16-00997
| Site Final | 10/10/2016 | 10/26/2016 | 10/26/2016 9:23:02 AM | P | NR |
|
|
SFH near completion. Landscaping/stabilization not yet installed. Temp BMP DI bag is installed. Trash container onsite. No violations
|
ESC16-00549
| General Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 8:35:06 AM | | PASS |
|
|
Modular building installed within Fedex shipping facility. BLD finaled, ESC conditions satisfied.
|
ESC16-00549
| DOC - Permit Finaled | 10/26/2016 | 10/26/2016 | 10/26/2016 8:34:27 AM | P | PASS |
|
|
|