Inspections for the day of: Tuesday, October 27, 1998.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRuss Owen
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD98-02052 INSP - Framing/Rough-in10/26/199810/27/199810/27/1998 12:00:00 AMAFAIL
left corrections.o!. Contact phone is [8666175].
BLD98-02792 INSP - Concrete10/26/199810/27/199810/27/1998 12:00:00 AMAPASS
footings.
BLD98-02809 INSP - Foundation10/27/199810/27/199810/27/1998 12:00:00 AMAPASS
Some confusion as to special inspection,contractor will address with architect,engineering was not done by ehm for foundations and was done as general design by architect,should not require special insp,if so they will has concrete test done ,none of other 5 buildings have ha d special inspection as it was never addressed by plan review,has been caught by a geaneral note on plan ,CONCRETE shall meet 3000 psi at 28 days.
BLD98-03289 INSP - Final10/27/199810/27/199810/27/1998 12:00:00 AMPPASS
storage shed.
BLD98-02616 INSP - Framing/Rough-in10/27/199810/27/199810/27/1998 12:00:00 AMPPASS
STEVE ###-#### SHEAR PANEL
MEC98-02976 INSP - Final10/28/199810/27/199810/27/1998 12:00:00 AMPPASS
MEC98-02976 INSP - Final10/28/199810/27/199810/27/1998 12:00:00 AMPPASS
MEC98-03586 INSP - Final10/27/199810/27/199810/27/1998 12:00:00 AMPPASS
gas log.6592
MEC98-03586 INSP - Final10/27/199810/27/199810/27/1998 12:00:00 AMPPASS
gas log.6592
BLD98-01802 INSP - Final10/27/199810/27/199810/27/1998 12:00:00 AMPFAIL
left correction
MEC98-03541 INSP - Framing/ Rough-in10/23/199810/27/199810/26/1998 12:00:00 AMACANC
sam ###-#### r/i pres test insp Cancelled by Hello! (Last update by [MLS]). Contact: [3362665].