ELE00-02868
| Final | 10/26/2000 | 10/27/2000 | 10/27/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 10/26/2000 at 11:35:43. Contact: ###-####. completed. 10/27/2000 12:44:31 PM
|
ELE00-03054
| Final | 10/26/2000 | 10/27/2000 | 10/27/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 10/26/2000 at 11:51:16. Contact: ###-####. completed. 10/27/2000 12:43:50 PM
|
ELE00-03603
| Final | 10/26/2000 | 10/27/2000 | 10/27/2000 12:00:00 AM | A | PASS |
|
|
BEN ###-#### FN . re-installation of smoke
detectors required by structural department, ok. 10/27/2000 12:46:52 PM
|
ELE00-04125
| Final | 10/26/2000 | 10/27/2000 | 10/27/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 10/26/2000 at 12:59:07. Contact: ###-####. meter/main service panel change. 10/28/2000 11:44:09 AM
|
ELE00-02984
| Electrical Rough-In | 10/26/2000 | 10/27/2000 | 10/27/2000 12:00:00 AM | P | CANC |
|
|
Scheduled by a contractor via Hello! on 10/26/2000 at 09:10:56. Contact: ###-####. wrong inspection request. 10/27/2000 12:54:18 PM
|
ELE00-02985
| Final | 10/26/2000 | 10/27/2000 | 10/27/2000 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 10/26/2000 at 09:41:18. Contact: ###-####. does not include modular cublicles. 10/27/2000 12:54:48 PM
|
ELE00-02984
| Final | 10/26/2000 | 10/27/2000 | 10/27/2000 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 10/26/2000 at 09:42:38. Contact: ###-####. does not include modular cublicles. only 1/2 of offices ready. 10/27/2000 12:55:25 PM 10/27/2000 12:56:38 PM
|
ELE00-02983
| Final | 10/26/2000 | 10/27/2000 | 10/27/2000 12:00:00 AM | P | PART |
|
|
RE-INSP--FN SHAWN- PAGER ###-####. does not include modular cublicles. 10/27/2000 12:57:08 PM
|
ELE99-03610
| Final | 10/26/2000 | 10/27/2000 | 10/27/2000 12:00:00 AM | P | PART |
|
|
Don ###-####.temporary occupancy. 10/28/2000 11:25:14 AM
|