ESC08-00884
| Random Inspection | 10/27/2008 | 10/27/2008 | 10/27/2008 4:36:53 PM | P | PASS |
|
|
ESC permit sign was posted. Site conditions were good.
|
BLD08-02214
| BLD-Conference | 10/27/2008 | 10/27/2008 | 10/27/2008 4:36:22 PM | P | DONE |
|
|
don Phone #: ###-####. On site to discuss 1hr. wall requirements with contractor for adu. It was decided to go with a 1hr wall up to ceiling and construct a draftstop in attic area and use 5/8 type X on ceiling in adu side.
|
BLD08-01868
| BLD-Framing/Rough-in | 10/24/2008 | 10/27/2008 | 10/27/2008 4:34:15 PM | P | NR |
|
|
Scheduled by a contractor via Hello! on 10/24/2008 at 10:43:54 AM. Contact: ###-####. Needs to pull mech permit and get ri insp. prior to framing insp. Contractor was notified.
|
BLD08-01652
| BLD-Framing/Rough-in | 10/24/2008 | 10/27/2008 | 10/27/2008 4:33:32 PM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 10/24/2008 at 3:29:43 PM. Contact: ###-####. Interior framing for batroom only. ok.
|
ESC08-00175
| Random Inspection | 10/27/2008 | 10/27/2008 | 10/27/2008 2:02:54 PM | P | PASS |
|
|
ESCX permit sign posted. site was clean.
|
BLD08-00464
| BLD-Framing/Rough-in | 10/27/2008 | 10/27/2008 | 10/27/2008 2:02:21 PM | P | PART |
|
|
chris Phone #: ###-####. Framing for detached garage only. ok.
|
BLD08-01182
| BLD-Framing/Rough-in | 10/24/2008 | 10/27/2008 | 10/27/2008 11:53:30 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 10/24/2008 at 1:20:32 PM. Contact: ###-####. Needs to get elec. ri insp. issues cleared up prior to framing insp. Called and left FMG (contractor) message. did not here back from contractor by 12:00pm.
|
BLD08-01729
| BLD-Final | 10/24/2008 | 10/27/2008 | 10/27/2008 10:21:58 AM | A | PASS |
|
|
ryan - please call 1/2 hr prior Phone #: ###-####
|
BLD08-01729
| DOC - Permit Finaled | 10/27/2008 | 10/27/2008 | 10/27/2008 10:21:44 AM | P | PASS |
|
|
Letter of compliance issued. Final ok.
|