FIR09-00082
| FIR-Aging Inspection | 10/27/2010 | 10/27/2010 | 10/28/2010 10:58:14 AM | | NR |
|
|
Work is in progress. Per Guy all of these AES inspections are being called in shortly.
|
FIR09-00081
| FIR-Aging Inspection | 10/27/2010 | 10/27/2010 | 10/28/2010 10:57:43 AM | | NR |
|
|
Work is in progress. Per Guy all of these AES inspections are being called in shortly.
|
FIR09-00077
| FIR-Aging Inspection | 10/27/2010 | 10/27/2010 | 10/28/2010 10:56:38 AM | | NR |
|
|
Work is in progress. Per Guy all of these AES inspections are being called in shortly.
|
FIR10-00297
| INSP-Conference | 10/27/2010 | 10/27/2010 | 10/28/2010 10:23:19 AM | P | DONE |
|
|
I spoke to Lori about theis projects status.
|
FIR10-00236
| INSP-Sprinkler Rough-in | 10/26/2010 | 10/27/2010 | 10/27/2010 2:37:57 PM | A | PASS |
|
|
The sprinkler piping above the private dining area is ok to cover. Coverage has not been provided yet in the accordian wall pocket.
|
BLD10-02227
| FIRE-Final Inspection | 10/27/2010 | 10/27/2010 | 10/27/2010 1:16:07 PM | P | PASS |
|
|
life safety passed
|
BLD09-01239
| FIRE-Final Inspection | 10/26/2010 | 10/27/2010 | 10/27/2010 11:41:43 AM | A | PASS |
|
|
life safety passed
|
FIR10-00101
| INSP-Final Inspection | 10/27/2010 | 10/27/2010 | 10/27/2010 11:40:16 AM | P | PASS |
|
|
Permit finaled. EOL verified.
|
BLD10-02029
| FIRE-Final Inspection | 10/26/2010 | 10/27/2010 | 10/27/2010 11:38:48 AM | A | PASS |
|
|
Life safety passed.
|
BLD09-01239
| FIRE-Alarm Testing | 10/26/2010 | 10/27/2010 | 10/27/2010 10:25:05 AM | A | PASS |
|
|
fire alarm testing passed.
|
FIR10-00482
| INSP-Final Inspection | 10/26/2010 | 10/27/2010 | 10/27/2010 8:47:54 AM | A | PASS |
|
|
Permit finaled
|