FIR14-00785
| INSP-Sprinkler Rough-in | 10/27/2014 | 10/27/2014 | 10/27/2014 3:39:14 PM | P | PART |
|
|
Sprinkler rough-in passed but I found an area at the north wall that is lacking sprinkler coverage. I will verify coverage at the final inspection. Piping is ok to cover.
|
FIR14-00397
| INSP-Sprinkler Rough-in | 10/27/2014 | 10/27/2014 | 10/27/2014 3:20:47 PM | P | PASS |
|
|
oh rough to cover passed. tenting passed. piping can be covered
|
FIR14-00397
| INSP-Supply line flush | 10/27/2014 | 10/27/2014 | 10/27/2014 3:03:52 PM | P | PASS |
|
|
ug flush passed
|
FIR14-00421
| INSP-Supply line flush | 10/27/2014 | 10/27/2014 | 10/27/2014 3:03:26 PM | P | PASS |
|
|
ug flush passed
|
FIR14-00424
| INSP-Supply line flush | 10/27/2014 | 10/27/2014 | 10/27/2014 3:03:10 PM | P | PASS |
|
|
ug flush passed
|
FIR14-00398
| INSP-Supply line flush | 10/27/2014 | 10/27/2014 | 10/27/2014 3:02:55 PM | P | PASS |
|
|
ug flush passed
|
FIR14-00420
| INSP-Supply line flush | 10/27/2014 | 10/27/2014 | 10/27/2014 3:02:40 PM | P | PASS |
|
|
ug flush passed
|
FIR14-00399
| INSP-Supply line flush | 10/27/2014 | 10/27/2014 | 10/27/2014 3:02:20 PM | P | PASS |
|
|
ug flush passed
|
FIR14-00423
| INSP-Supply line flush | 10/27/2014 | 10/27/2014 | 10/27/2014 3:02:00 PM | P | PASS |
|
|
ug flush passed
|
FIR13-00697
| INSP-Sprinkler Rough-in | 10/27/2014 | 10/27/2014 | 10/27/2014 12:08:42 PM | P | PART |
|
|
air test on preaction system started at 10:00am with pressure marked on guage.
|
BLD13-02595
| FIRE-Final Inspection | 10/24/2014 | 10/27/2014 | 10/27/2014 12:07:53 PM | A | PASS |
|
|
Life safety passed
|
FIR14-00446
| INSP-Final Inspection | 10/24/2014 | 10/27/2014 | 10/27/2014 10:14:26 AM | A | PASS |
|
|
Permit finaled
|