Inspections for the day of: Tuesday, October 27, 2015.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDave Hannah
TitleBLD-COM/RES INSPECTOR
Phone #794-1967
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD15-02346 BLD-Framing/Rough-in10/26/201510/27/201510/28/2015 12:08:03 PMPPART
This project is operating during the night hours. If at all possible, a late in the day inspection is preferable. Please contact me an hour prior to inspection if at all possible so that I may meet onsite for access and inspection.
Thank you, Chris Palmer. Phone #: ###-#### Inspection requested via web by Chris Palmer phase one ok to one side needs to fire holes in floor
GCB15-00047 GCB-Framing10/28/201510/27/201510/28/2015 12:06:14 PMPDONE
Manny ###-####
GCB15-00053 GCB-Final10/28/201510/27/201510/28/2015 12:05:55 PMADONE
Shawn ###-####
BLD15-02905 BLD-Framing/Rough-in10/26/201510/27/201510/28/2015 6:35:36 AMPPASS
Renee Phone #: ###-####
BLD15-03499 BLD-Final10/27/201510/27/201510/27/2015 2:04:12 PMPPASS
Roofing complete. Phone #: ###-#### Inspection requested via web by Richard Murray
BLD15-03499 DOC - Permit Finaled10/27/201510/27/201510/27/2015 2:03:41 PMPPASS
BLD13-03502 BLD-Wall cover10/27/201510/27/201510/27/2015 1:35:56 PMPPASS
Vanessa Phone #: ###-####
BLD15-03829 BLD-Framing/Rough-in10/27/201510/27/201510/27/2015 1:25:32 PMPPEND
Monica Phone #: ###-#### ok to insulate but three ply lvl in ceiling is over spanned need engineering for suport locations
BLD15-03876 BLD-Foundation10/26/201510/27/201510/27/2015 11:46:24 AMAPASS
Damien Phone #: ###-####
GCB15-00053 GCB-Final10/27/201510/27/201510/27/2015 10:46:55 AMAPASS
Shawn ###-####
BLD14-03434 BLD-Conference10/26/201510/27/201510/27/2015 10:46:12 AMADONE
Phil Phone #: ###-####
BLD15-03512 BLD-Framing/Rough-in10/26/201510/27/201510/27/2015 9:18:02 AMAPASS
Call 20 mins before // Dan Phone #: ###-####