BLD02-01306
| BLD-Final | 10/25/2002 | 10/28/2002 | 10/28/2002 12:00:00 AM | A | PASS |
|
|
ok for l/c 10/28/2002 9:38:38 AM
|
BLD02-01958
| BLD-Footing | 10/25/2002 | 10/28/2002 | 10/28/2002 12:00:00 AM | A | PART |
|
|
###-#### robert need soil compaction test for fill under footings. rebar ok / ok to pour pending approval results from soil report. 10/28/2002 9:09:35 AM
|
BLD02-00219
| BLD-Final | 10/25/2002 | 10/28/2002 | 10/28/2002 12:00:00 AM | A | PASS |
|
|
###-#### ###-####final ok c/o 10/28/2002 4:27:03 PM
|
BLD02-01305
| BLD-Final | 10/28/2002 | 10/28/2002 | 10/28/2002 12:00:00 AM | A | PASS |
|
|
need cdhd sign off. final perm ok upon sign off. 10/28/2002 9:41:00 AM
|
BLD02-02571
| BLD-Final | 10/28/2002 | 10/28/2002 | 10/28/2002 12:00:00 AM | P | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung l/c ok 10/28/2002 4:19:41 PM
|
BLD02-02563
| BLD-Footing | 10/28/2002 | 10/28/2002 | 10/28/2002 12:00:00 AM | P | PART |
|
|
###-#### ###-####rebar ok depth of ft only 10 to 12 inches below exting grade will need to address at back fill and drainage. 10/28/2002 2:00:10 PM
|
BLD02-00756
| BLD-Framing/Rough-in | 10/28/2002 | 10/28/2002 | 10/28/2002 12:00:00 AM | P | NR |
|
|
ready after 2 ###-#### ele no sticker no stop for insp until approval. 10/28/2002 2:06:22 PM
|
BLD02-00786
| BLD-Final | 10/28/2002 | 10/28/2002 | 10/28/2002 12:00:00 AM | P | PASS |
|
|
###-####
|
MEC02-03115
| Rough-in | 10/25/2002 | 10/28/2002 | 10/28/2002 12:00:00 AM | P | PASS |
|
|
late please ###-####
|
MEC02-03115
| Pressure Test | 10/25/2002 | 10/28/2002 | 10/28/2002 12:00:00 AM | P | DONE |
|
|
gas co. cert gas line 10/28/2002 4:46:17 PM
|