FIR06-00072
| INSP-Final Inspection | 10/28/2008 | 10/28/2008 | 10/30/2008 10:57:53 AM | A | DONE |
|
|
Scope of work completed by a different contractor.
|
FIR08-00239
| INSP-Sprinkler Rough-in/Hydro | 10/27/2008 | 10/28/2008 | 10/28/2008 5:50:49 PM | P | PART |
|
|
Building #3 2nd floor wet and dry system rough-in inspections passed with the exception of 5 concealed combustible attic pockets in need of sprinkler protection-or to be filled entirely with insulation per NFPA 13 exceptions including 2 pockets at the dry system, also noted one upright head to be relocated due to truss obstructions. See annotations on stamped plan set for locations.
|
FIR08-00715
| INSP-Final Inspection | 10/28/2008 | 10/28/2008 | 10/28/2008 5:45:06 PM | P | PASS |
|
|
Rough-in and final inspections completed at the same time, fire sprinkler permit finaled.
|
BLD06-02892
| FIRE-Final Inspection | 10/27/2008 | 10/28/2008 | 10/28/2008 3:33:57 PM | P | PASS |
|
|
C/N completed, gate hardware is acceptable, life safety inspection passed.
|
BLD07-03106
| FIRE-Final Inspection | 10/27/2008 | 10/28/2008 | 10/28/2008 3:32:46 PM | P | FAIL |
|
|
Provide missing max. occupant load signs, remove keyed locking deadbolt above the panic hardware at the second exit, install exit sign/EM light above the main door per approved plan. See fire code review notes items 7,8,9, and 12 for details.
|
BLD07-00337
| FIRE-Conference | 10/28/2008 | 10/28/2008 | 10/28/2008 1:20:07 PM | A | DONE |
|
|
Scope of permit work is not yet completed for inspection at this time.
|
FIR08-00544
| INSP-Sprinkler Rough-in/Hydro | 10/28/2008 | 10/28/2008 | 10/28/2008 1:19:05 PM | A | PART |
|
|
OH system modifications approved as noted on plans to date.
|
BLD08-00572
| FIRE-Final Inspection | 10/28/2008 | 10/28/2008 | 10/28/2008 1:17:56 PM | A | FAIL |
|
|
Need project related fire sprinkler work completed prior to BLD permit final.
|