BLD09-00295
| FIRE-Conference | 10/28/2009 | 10/28/2009 | 10/28/2009 4:36:42 PM | P | DONE |
|
|
On site conference regarding fire code review notes and items needed for final including EM lighting, occ. load sign, PFE's, door hardware, fire sprinkler coverage, etc.
|
FIR09-00479
| INSP-Sprinkler Rough-in/Hydro | 10/28/2009 | 10/28/2009 | 10/28/2009 4:34:54 PM | P | NR |
|
|
Insulation work incomplete, not ready for inspection at this time per contractor.
|
BLD09-01289
| FIRE-Final Inspection | 10/28/2009 | 10/28/2009 | 10/28/2009 4:33:56 PM | P | PASS |
|
|
Fire life safety completed satisfactory.
|
FIR09-00413
| INSP-Final Inspection | 10/27/2009 | 10/28/2009 | 10/28/2009 4:33:15 PM | A | PASS |
|
|
Fire sprinkler final inspection passed, correction items finished, permit final approved.
|
BLD09-01327
| FIRE-Final Inspection | 10/27/2009 | 10/28/2009 | 10/28/2009 4:32:17 PM | A | FAIL |
|
|
Existing fire sprinkler coverage will need modifications due to remodel work, see fire code review notes for details pertaining.
|
BLD09-01680
| FIRE-Final Inspection | 10/27/2009 | 10/28/2009 | 10/28/2009 4:30:02 PM | A | PASS |
|
|
Fire life safety passed inspection.
|
FIR09-00525
| INSP-Final Inspection | 10/27/2009 | 10/28/2009 | 10/28/2009 4:29:24 PM | A | PASS |
|
|
Remainder of fire sprinkler permit work passed site inspection, final okayed.
|