ELE11-00647
| ELE-Aging Inspection | 10/28/2011 | 10/28/2011 | 11/1/2011 10:37:16 AM | | PASS |
|
|
still under construction
|
ELE11-02041
| Final | 10/28/2011 | 10/28/2011 | 10/28/2011 1:44:42 PM | P | PASS |
|
|
THANKS, BOB Phone #: ###-#### >> Inspection requested via web by Bob Glenn final ok Elect. contractor agrees to provide GFCI protection on switches in shower entry.
|
ELE11-02367
| Electrical Rough-In | 10/28/2011 | 10/28/2011 | 10/28/2011 12:32:57 PM | P | PASS |
|
|
Please call with arrival time to ensure access. Thank You Phone #: ###-#### >> Inspection requested via web by Eric Brown rough-in ok cover floor heat master bath
|
ELE11-02083
| Final | 10/28/2011 | 10/28/2011 | 10/28/2011 12:15:51 PM | P | PASS |
|
|
scheduled under wrong permit final ok
|
ELE11-02457
| Rough-In Permanent Service | 10/27/2011 | 10/28/2011 | 10/28/2011 9:58:20 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Dan Rohl rough-in p/s u/g n ok
|
ELE11-02369
| Final | 10/27/2011 | 10/28/2011 | 10/28/2011 9:17:00 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Tate final ok 1 st phase lighting retro,UL listed partition walls
|
ELE11-02253
| Final | 10/26/2011 | 10/28/2011 | 10/28/2011 8:55:16 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Barbara Szurgot final ok
|
ESC11-00764
| Site Preparation | 10/28/2011 | 10/28/2011 | 10/28/2011 8:31:26 AM | | PASS |
|
|
construction has not started yet, site clean
|
ELE11-02408
| Electrical Rough-In | 10/27/2011 | 10/28/2011 | 10/28/2011 8:19:40 AM | A | PASS |
|
|
REINSPECTION Phone #: ###-#### >> Inspection requested via web by MARK PINNEY rough-in ok cover kitchen area, corrections made
|
ELE11-02453
| Rough-In Permanent Service | 10/27/2011 | 10/28/2011 | 10/28/2011 7:56:58 AM | A | NR |
|
|
GARY Phone #: ###-####
|