BLD13-02895
| FIRE-Final Inspection | 10/28/2013 | 10/28/2013 | 10/28/2013 5:19:07 PM | P | FAIL |
|
|
Correction items include; building address, need current annual certification for the existing fire extinguishers, provide access to one locked office, install approved hardware at the main entry/exit door.
|
FIR13-00101
| INSP-Final Inspection | 10/28/2013 | 10/28/2013 | 10/28/2013 5:16:11 PM | P | PASS |
|
|
UG fire supply line permit approved for final status.
|
FIR13-00243
| INSP-Final Inspection | 10/25/2013 | 10/28/2013 | 10/28/2013 5:14:20 PM | A | PASS |
|
|
Fire sprinkler work passed final inspection.
|
BLD13-02290
| FIRE-Final Inspection | 10/25/2013 | 10/28/2013 | 10/28/2013 11:22:00 AM | A | PASS |
|
|
Fire life safety inspection completed satisfactory.
|
FIR13-00539
| INSP-Final Inspection | 10/28/2013 | 10/28/2013 | 10/28/2013 11:21:07 AM | A | PASS |
|
|
Scope of work completed, final walkthrough passed. Fire sprinkler permit finaled.
|
BLD13-02869
| FIRE-Final Inspection | 10/25/2013 | 10/28/2013 | 10/28/2013 11:19:51 AM | A | PASS |
|
|
Life safety finaled.
|