FIR14-00750
| INSP-Sprinkler Rough-in | 10/27/2015 | 10/28/2015 | 10/28/2015 12:26:37 PM | A | PART |
|
|
Started 24 hour air test of dry pipe fire sprinkler system for Bldg. K. Will reinspect tomorrow same time (9:00am) to confirm holding after 24 hours.
|
FIR15-00329
| INSP-Supply line flush | 10/27/2015 | 10/28/2015 | 10/28/2015 12:24:16 PM | A | FAIL |
|
|
Rough inspection of fire service underground supply line (south side) into convention center portion of the building. U/G supply line penetrates building foundation without proper clearanace. Contractor agreed to remove pipe as needed to provide a clearance sleeve (10") around the 6" supply line.
|