BLD03-00286
| BLD-Conference | 10/28/2003 | 10/29/2003 | 10/29/2003 12:00:00 AM | A | PASS |
|
|
Joe; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Extend permit 180 days. 10/29/2003 11:06:01 AM
|
BLD03-01431
| BLD-Foundation | 10/27/2003 | 10/29/2003 | 10/29/2003 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 10/27/2003 at 5:23:40 PM. Contact: ###-####.
|
BLD03-02469
| BLD-Framing/Rough-in | 10/28/2003 | 10/29/2003 | 10/29/2003 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 10/28/2003 at 9:14:11 AM. Contact: ###-####.
|
BLD03-02095
| BLD-Energy code compliance | 10/28/2003 | 10/29/2003 | 10/29/2003 12:00:00 AM | P | PASS |
|
|
Allen; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
BLD03-02501
| BLD-Footing | 10/28/2003 | 10/29/2003 | 10/29/2003 12:00:00 AM | P | PASS |
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD03-02525
| BLD-Footing | 10/29/2003 | 10/29/2003 | 10/29/2003 12:00:00 AM | P | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Ken Litzinger
|
BLD03-01905
| BLD-Framing/Rough-in | 10/29/2003 | 10/29/2003 | 10/29/2003 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 10/29/2003 at 9:09:32 AM. Contact: ###-####. C/N 10/29/2003 2:47:12 PM
|
BLD03-01915
| BLD-Energy code compliance | 10/29/2003 | 10/29/2003 | 10/29/2003 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 10/29/2003 at 9:10:33 AM. Contact: ###-####.
|
BLD03-02389
| BLD-Conference | 10/29/2003 | 10/29/2003 | 10/29/2003 12:00:00 AM | P | PASS |
|
|
per Jim Removed Stop Work.....owner hired an experienced contractor to help finish living room framing.....owner ordered Mfg trussed from BMC..... 10/29/2003 2:21:07 PM
|
BLD03-00319
| BLD-Conference | 10/29/2003 | 10/29/2003 | 10/29/2003 12:00:00 AM | P | PART |
|
|
andy; Phone #: ###-#### Internet Inspection Request from: Annette Moore C/N Verify 6" slab....Resubmit shows column conn to slab but no details for connection to existing bldg....Eng to provide stamped detal .... Need fire and zoning final prior to struct......Cert of Compl OK when complete. 10/29/2003 1:06:24 PM
|
BLD03-02389
| BLD-Footing | 10/29/2003 | 10/29/2003 | 10/29/2003 12:00:00 AM | P | PASS |
|
|
zijad; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Removed wood flooring from above new slab and poured concrete "cap" over slab to level flush with existing floor. 10/29/2003 2:17:27 PM 10/29/2003 2:18:59 PM
|
BLD03-01273
| BLD-Foundation | 10/29/2003 | 10/29/2003 | 10/29/2003 12:00:00 AM | P | PASS |
|
|
james; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|