ELE14-02738
| Conference | 10/2/2014 | 10/3/2014 | 10/3/2014 3:34:53 PM | P | DONE |
|
|
Raymond Phone #: ###-#### Spoke with homeowner about Grounding,conductor sizing for 30 ampere 120 volt RV receptacle.
|
ELE14-02583
| Rough-In Permanent Service | 10/1/2014 | 10/3/2014 | 10/3/2014 2:51:23 PM | P | PASS |
|
|
Please contact Gary ###-#### with any questions. Phone #: ###-#### Inspection requested via web by Tracy Robertson rough-in p/s u/g n ok
|
MIS14-00235
| ELE-Conference | 9/30/2014 | 10/3/2014 | 10/3/2014 11:00:11 AM | A | NH |
|
|
No access- occupant at work,
|
ELE14-02696
| Final | 10/2/2014 | 10/3/2014 | 10/3/2014 10:19:19 AM | A | NR |
|
|
Mark Phone #: ###-#### Not ready for final at this time.
|
ELE14-02696
| Permanent Service | 10/3/2014 | 10/3/2014 | 10/3/2014 10:17:11 AM | A | PASS |
|
|
Mark Phone #: ###-#### 60ampere RV service p/s o/h n ok
|
ELE14-02575
| Electrical Rough-In | 10/2/2014 | 10/3/2014 | 10/3/2014 9:45:56 AM | A | PASS |
|
|
Dan Phone #: ###-#### rough-in ok cover ceiling grid
|
ELE13-03105
| Electrical Rough-In | 10/2/2014 | 10/3/2014 | 10/3/2014 8:53:24 AM | A | PASS |
|
|
Under ground east side thickener building Phone #: ###-#### Inspection requested via web by matt miller Rough-in ok cover from building to vault
|
ELE14-02224
| Final | 10/2/2014 | 10/3/2014 | 10/3/2014 8:27:44 AM | A | PASS |
|
|
Call ben if any questions Phone #: ###-#### Inspection requested via web by Ben final ok
|