Inspections for the day of: Tuesday, October 30, 2001.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR01-00421 INSP-Sprinkler Rough-in/Hydro10/29/200110/30/200110/30/2001 12:00:00 AMAPASS
Aboveground hydro test OK 10/29/2001 4:00:31 PM
FIR01-00421 INSP-Final Inspection10/29/200110/30/200110/30/2001 12:00:00 AMANR
Not ready for final. Alarm system and outside canopy to be finished. 10/29/2001 4:00:12 PM
FIR01-00370 INSP-Sprinkler Rough-in/Hydro10/29/200110/30/200110/30/2001 12:00:00 AMAPASS
Above ground hydro test OK. FDC to be hydro yet. 10/30/2001 12:47:55 PM
BLD01-01045 FIRE-Final Inspection10/29/200110/30/200110/30/2001 12:00:00 AMAFAIL
1 hour wall needs to be completed and duct detector is to be installed on mech unit in basement 10/31/2001 9:14:50 AM
BLD01-02555 FIRE-Final Inspection10/30/200110/30/200110/30/2001 12:00:00 AMPPART
Fire sprinkler system is OK and signed off. Smoke detector and fire damper operation on the fire alarm system needs to be tested. 10/31/2001 9:17:05 AM
MIS01-00213 FIR-Final10/29/200110/30/200110/30/2001 12:00:00 AMPFAIL
Left correction notice on requirements for doors, exit lights, emergency lights and fire extinguishers. 10/31/2001 9:15:51 AM
FIR01-00505 INSP-Sprinkler Rough-in/Hydro10/29/200110/30/200110/30/2001 12:00:00 AMPPASS
Left correction notice. Install hose station outlet, pendents overspace in corr. 110, pendents not installed in restroom and computer room, taped heads in restroom, hangers missing, FDC leaking, install alarm bell, verify test orfice matches head, provide letter stating heads are installed in canopies. 10/31/2001 9:19:52 AM