GCB14-00099
| FIRE-Final Inspection | 10/29/2015 | 10/30/2015 | 10/30/2015 3:11:22 PM | A | PART |
|
|
Fire life-safety inspection for the south wing, including exit signage and emergency lighting test. All tested OK. Conducted partial fire alarm testing in this wing, however fire sprinkler flow testing could not be performed. Fire door hardware installation (unit doors, stairwell doors and fire cross corridor fire doors) is still a works in progress and would need to be completed prior to TCO of this wing. NOTE: The existing TCO area should include up to units 114, 215-217 and 313-315.
|
GCB14-00099
| FIRE-Conference | 10/29/2015 | 10/30/2015 | 10/30/2015 3:05:47 PM | A | DONE |
|
|
Called to discuss inspections needed today.
|
NAF15-00006
| INSP-Final | 10/29/2015 | 10/30/2015 | 10/30/2015 3:04:41 PM | A | CANC |
|
|
Fire sprinkler contractors not available to conduct inspection, including flow tests of the fire sprinkler risers.
|
NAF15-00014
| INSP-Alarm Testing | 10/29/2015 | 10/30/2015 | 10/30/2015 3:03:16 PM | A | PART |
|
|
Conducted test of fire alarm system for the south wing - north wing already tested for TCO of that wing. Tested unit SDs and CO dtectors, common area SDs in corridors, elevator recall functions, etc. All tested OK. NOTE: Fire sprinkler contractor was not available to conduct flow tests for the fire sprinkler systems. Also did not have enough time to test FSDs. These will have to be tested at next inspection.
|
NAF15-00024
| INSP-Supply line flush | 10/30/2015 | 10/30/2015 | 10/30/2015 3:03:16 PM | P | CANC |
|
|
Will call to reschedule on Monday. Ran out of time for this inspection, and Anthony said that he can wait till then.
|
FIR14-00715
| INSP-Final Inspection | 10/27/2015 | 10/30/2015 | 10/30/2015 11:15:20 AM | A | PART |
|
|
Test of fire alarm system for SNF Bldg. K, including water flow and tampers for the fire sprinkler systems (wet and dry). All tested OK. Test of SDs, MPs, FSDs, Duct Detectors for HVAC shutdown ( 5 units), notification devices. All components tested OK. NOTE: Hood and Duct FP system not installed yet, and interface with egress hardware (mag-locks) not tested as these doors and hardware are still being installed. Otherwise, Bldg. K fire alarm system test is completed.
|