Inspections for the day of: Friday, October 30, 2015.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-00641 Aging Inspection10/30/201510/30/201510/30/2015 4:23:29 PM PASS
Work complete. No outstading ESC corrections needed.
ESC14-00544 General Inspection10/30/201510/30/201510/30/2015 4:22:56 PM PASS
ESC15-00641 DOC - Permit Finaled10/30/201510/30/201510/30/2015 4:22:07 PMPPASS
ESC15-00636 Aging Inspection10/30/201510/30/201510/30/2015 4:21:52 PM CANC
ESC14-00328 General Inspection10/30/201510/30/201510/30/2015 4:21:42 PM CANC
ESC14-00296 General Inspection10/30/201510/30/201510/30/2015 4:21:32 PM CANC
ESC14-00462 General Inspection10/30/201510/30/201510/30/2015 4:21:22 PM PASS
pool in progress. No sediment leaving site, yard is landscaped/vegetated.
ESC15-01443 Site Preparation10/30/201510/30/201510/30/2015 2:17:35 PMPPASS
Stinker soil removal...

Work to begin Monday. 2 day project to remove contaminated soils. Excavated trench will be loaded into containment barrels and hauled away. Remaining soils will be vacuumed up with Vac truck and disposed of legally at landfill.

Permit sign posted at area of work. Approved.
ESC14-01052 General Inspection10/30/201510/30/201510/30/2015 2:02:18 PM PASS
No trackout or discharges from Asheville Commons. WIP on 4-plexes, perimeter BMPs installed, stormwater contained on site.
ESC15-00630 Aging Inspection10/30/201510/30/201510/30/2015 2:01:00 PM CANC
ESC14-00588 General Inspection10/30/201510/30/201510/30/2015 12:01:31 PM PASS
WIP. Entry road apron for the District is near completion. Parkcenter median has been swept, no significant trackout occuring currently. RP onsite. No corrections at this time.
ESC13-01279 General Inspection10/30/201510/30/201510/30/2015 11:40:53 AM PASS
Lucky Harris 13/Harris Crossing. New set of SFHs in progress at south end of sub. No trackout or discharges from site. No windblown litter due to trash containers. DIs protected, limits of disturbance respected with vegetative perimeter in addition to some sediment control BMPs. No corrections.
ESC15-01331 Site Preparation10/30/201510/30/201510/30/2015 11:38:06 AMPPASS
Phone #: ###-#### Inspection requested via web by Weston Wagner


Approved for construction. Subdivision BMPs installed. Hunter Homes projects are in compliance.
ESC15-01328 Site Preparation10/30/201510/30/201510/30/2015 11:37:37 AMPPASS
Phone #: ###-#### Inspection requested via web by Weston Wagner

Approved for construction. Subdivision BMPs installed. Hunter Homes projects are in compliance.
ESC15-00554 Aging Inspection10/30/201510/30/201510/30/2015 11:29:25 AM PASS
WIP on interior and need to finish landscaping. Adjacent lot is only open lot on Woodcutter and will need cleaning if new SFH does not start. No issues in Mill District Square. No sediment runoff, workers staying off muddy areas.
ESC15-01418 Site Preparation10/29/201510/30/201510/30/2015 10:29:57 AMAPASS
would like call ahead; Curt Phone #: ###-####

Will leave existing driveway through duration of new garage construction. Work will begin next week. Low risk, RP familiar with ESC requirements and conditions.
ESC14-00488 General Inspection10/30/201510/30/201510/30/2015 9:34:36 AM PASS
Home near completion. Yard is now landscaped. Some acivity still occuring, will check for final next inspection.
ESC15-00615 Aging Inspection10/30/201510/30/201510/30/2015 8:45:57 AM PASS
Project complete. No disturbed area or loose sediment at site. All permits finaled. Approved.
ESC15-00615 DOC - Permit Finaled10/30/201510/30/201510/30/2015 8:45:23 AMPPASS
ESC14-01063 General Inspection10/30/201510/30/201510/30/2015 8:44:53 AM CANC