FIR04-00207
| FIR-Aging Inspection | 10/31/2005 | 10/31/2005 | 11/1/2005 1:06:08 PM | | NR |
|
|
Jim is following up
|
BLD05-02429
| FIRE-Final Inspection | 10/31/2005 | 10/31/2005 | 11/1/2005 9:50:41 AM | P | FAIL |
|
|
elliott; Phone #: ###-#### Provide annual inspection for the sprinkler system, provide fire extinguisher, hardware on the two main exits is ok but the hardware from this tenant to the common corridor needs to be ada compliant. Also a permanant solution needs to be provided for the egress from the common restroom/corridor.
|
FIR05-00271
| INSP-Sprinkler Rough-in | 10/31/2005 | 10/31/2005 | 10/31/2005 4:06:32 PM | P | PASS |
|
|
Underground supply piping is ok to cover.
|
FIR05-00600
| INSP-Sprinkler Rough-in | 10/31/2005 | 10/31/2005 | 10/31/2005 3:33:26 PM | P | CANC |
|
|
Not ready yet per Sam.
|
FIR05-00519
| INSP-Conference | 10/31/2005 | 10/31/2005 | 10/31/2005 2:39:54 PM | P | DONE |
|
|
I spoke to Mary and notified her about the switch to shut off the strobes located inside a facp in the 3rd floor broom closet. The 5th floor has been removed from it but it still controls the 3rd, 4th and 6th floors.
|
FIR03-00586
| INSP-Final Inspection | 10/31/2005 | 10/31/2005 | 10/31/2005 2:38:25 PM | P | PASS |
|
|
Fire alarm permit finaled
|
FIR04-00004
| INSP-Final Inspection | 10/31/2005 | 10/31/2005 | 10/31/2005 2:35:32 PM | P | NR |
|
|
I left a correction notice with Diane at the front desk that if all permits had not been finaled by 11/11/05 the affected areas of the building would be shutdown. I also spoke to scott, the building owner. See building review comments.
|
BLD05-00261
| FIRE-Final Inspection | 10/31/2005 | 10/31/2005 | 10/31/2005 2:33:38 PM | P | FAIL |
|
|
Provide verification of the cfm rating for the roof top units and lower and tag the fire extinguisher in the storage room.
|
BLD05-01608
| FIRE-Final Inspection | 10/28/2005 | 10/31/2005 | 10/31/2005 10:53:27 AM | A | FAIL |
|
|
Duct detectors still need connected and tested. Also need the door hardware in the basement installed.
|
FIR05-00557
| INSP-Sprinkler Rough-in | 10/28/2005 | 10/31/2005 | 10/31/2005 10:35:11 AM | A | FAIL |
|
|
An additional branchline has been added for a rear corridor. This branchline is supplied from the new 3x2 mechanical tee installed for upright heads along the separation wall between sales and stockroom. It is not sized the same as the new line shown on the approved plans. Additional heads have been deleted in the sales area under the open meshed hanging fixture and at the main entrance. Resubmit plans showing these additions and deletions.
|
FIR05-00696
| INSP-Sprinkler Rough-in | 10/28/2005 | 10/31/2005 | 10/31/2005 10:32:34 AM | A | FAIL |
|
|
Pendant heads in sales area are overspaced as noted on the approved plans that did not arrive to the job site until this morning.
|