Inspections for the day of: Monday, October 31, 2005.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD05-00493 BLD-Foundation10/30/200510/31/200510/31/2005 3:29:24 PMPPART
Scheduled by a contractor via Hello! on 10/30/2005 at 9:16:09 PM. Contact: ###-####. @nd lift at masonry retaining wall. noted incorrect rebar placement at corners and around openings. Correct rebar has been placed at 2nd lift. Preivious lifts have incorrect rebar placement. Need engineer ok on work in place.
BLD05-01735 BLD-Other10/28/200510/31/200510/31/2005 2:52:24 PMPDEFR
Mason re-grout tim ###-####. Masonry was inspected by special inspector.
BLD05-01661 BLD-Framing/Rough-in10/28/200510/31/200510/31/2005 1:48:47 PMPPART
tim; Phone #: ###-#### Internet Inspection Request from: Barbara Moore. Bldg. A trusses and roog sheeting. Contractor to get RFI from engineer for deletion of hangars on blocking and straps at east end of roof.
BLD05-02805 BLD-Footing10/28/200510/31/200510/31/2005 11:12:59 AMAPART
kevin; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD05-02801 BLD-Footing10/28/200510/31/200510/31/2005 11:12:46 AMAPART
kevin; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD05-02769 BLD-Footing10/28/200510/31/200510/31/2005 11:12:35 AMAPART
###-#### - kevin
BLD05-02233 BLD-Foundation10/27/200510/31/200510/31/2005 9:23:21 AMANR
j jones; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles