FIR06-00468
| INSP-Final Inspection | 10/30/2006 | 10/31/2006 | 11/2/2006 12:24:03 PM | A | CANC |
|
|
No time to complete inspection request.
|
FIR06-00502
| INSP-Alarm Testing | 10/31/2006 | 10/31/2006 | 11/1/2006 2:26:49 PM | P | NR |
|
|
dan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD06-02033
| FIRE-Final Inspection | 10/31/2006 | 10/31/2006 | 10/31/2006 4:26:15 PM | P | FAIL |
|
|
Need to lower the mounting height of the provided fire extinguishers to no higher than 48" AFF, provide a visual indicator at the main entry/exit door.
|
BLD06-00278
| FIRE-Final Inspection | 10/30/2006 | 10/31/2006 | 10/31/2006 4:23:56 PM | A | PASS |
|
|
Life safety inspection for the shell building passed.
|
BLD06-02684
| FIRE-Final Inspection | 10/31/2006 | 10/31/2006 | 10/31/2006 3:44:56 PM | P | FAIL |
|
|
The installation of the new overhead door will require a fire sprinkler system modification with an associated FIR permit.
|
BLD06-02125
| FIRE-Final Inspection | 10/31/2006 | 10/31/2006 | 10/31/2006 3:02:52 PM | P | PASS |
|
|
Life safety inspection passed.
|
FIR06-00684
| INSP-Final Inspection | 10/30/2006 | 10/31/2006 | 10/31/2006 2:35:25 PM | A | PART |
|
|
Resubmitted plans verified on site to reflect the installation, rough-in is good for cover.
|
BLD06-02738
| FIRE-Final Inspection | 10/30/2006 | 10/31/2006 | 10/31/2006 2:09:44 PM | P | PASS |
|
|
Field inspection passed, the provided PFE must have a current certification tag which must be done prior to structural final per agreement.
|
BLD06-02486
| FIRE-Final Inspection | 10/30/2006 | 10/31/2006 | 10/31/2006 2:07:44 PM | A | PASS |
|
|
Items on previous c/n have been verified for completion, inspection passed.
|
BLD06-02515
| FIRE-Final Inspection | 10/30/2006 | 10/31/2006 | 10/31/2006 1:36:39 PM | P | PASS |
|
|
Life safety inspection passed per final field inspection completed by S. Arellano.
|
FIR06-00679
| INSP-Final Inspection | 10/31/2006 | 10/31/2006 | 10/31/2006 1:35:24 PM | P | PASS |
|
|
Per field inspection completed by S. Arellano, the required corrections have been made. Fire sprinkler permit finaled.
|
BLD06-02743
| FIRE-Sprinkler Rough-in | 10/30/2006 | 10/31/2006 | 10/31/2006 1:00:04 PM | P | FAIL |
|
|
Missing fire extinguisher, contractor must also request project related fire sprinkler permit for inspection and final approval prior to life safety final.
|
FIR06-00712
| INSP-Sprinkler Rough-in | 10/30/2006 | 10/31/2006 | 10/31/2006 12:57:49 PM | A | PART |
|
|
Rough-in inspection is satisfactory per previous visit by T. Cobbley.
|
FIR06-00695
| INSP-Sprinkler Rough-in | 10/30/2006 | 10/31/2006 | 10/31/2006 12:56:49 PM | A | PART |
|
|
OH rough-in inspection is okay per T. Cobbley.
|
FIR06-00694
| INSP-Sprinkler Rough-in | 10/30/2006 | 10/31/2006 | 10/31/2006 12:55:36 PM | A | PART |
|
|
Rough-in inspection is acceptable per T. Cobbley.
|
FIR06-00375
| INSP-Sprinkler Rough-in/Hydro | 10/30/2006 | 10/31/2006 | 10/31/2006 12:54:39 PM | A | PART |
|
|
AG hydrostatic test for the two wet systems passed, noted to contractor the FDC piping will need to be hydro tested as well.
|
FIR06-00340
| INSP-Final Inspection | 10/30/2006 | 10/31/2006 | 10/31/2006 12:50:58 PM | A | PASS |
|
|
UG fire supply line permit finaled.
|
FIR06-00024
| FIR-Aging Inspection | 10/31/2006 | 10/31/2006 | 10/31/2006 12:06:12 PM | | DEFR |
|
|
|
FIR05-00536
| INSP-Sprinkler Rough-in/Hydro | 10/30/2006 | 10/31/2006 | 10/31/2006 11:59:24 AM | A | PART |
|
|
Inspection for overhead cover at the drop ceilings in the 1st floor corridor to the north tower and the hard lid on the 3rd floor stair tower #4 landing are acceptable for cover.
|
MIS06-00278
| FIR-Final | 10/30/2006 | 10/31/2006 | 10/31/2006 11:39:02 AM | A | FAIL |
|
|
Need to provide a certification tag for the provided PFE and mount on the wall as discussed, provide covers on two open electrical junction boxes, keyed locking hardware at the back exit door is not allowed.
|
FIR06-00828
| INSP-Final Inspection | 10/30/2006 | 10/31/2006 | 10/31/2006 11:08:23 AM | A | PASS |
|
|
Fire sprinkler work passed field inspection, permit finaled.
|
FIR06-00545
| INSP-Sprinkler Rough-in/Hydro | 10/30/2006 | 10/31/2006 | 10/31/2006 10:44:16 AM | A | DEFR |
|
|
Phone #: ###-#### Internet Inspection Request from: Rob Puckett Inspection rescheduled for 11/1.
|
FIR06-00690
| INSP-Alarm Testing | 10/26/2006 | 10/31/2006 | 10/31/2006 10:41:52 AM | A | DEFR |
|
|
Phone #: ###-#### Internet Inspection Request from: Ken Campbell Inspection rescheduled for 11/1.
|
BLD06-00856
| BLD-Final | 10/31/2006 | 10/31/2006 | 10/31/2006 12:00:00 AM | P | CANC |
|
|
Gonzalo, reinspect = ); Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt nOTE INSPECTOR TO ASK TO CANCEL
|