ESC12-01035
| General Inspection | 10/31/2013 | 10/31/2013 | 10/31/2013 4:19:23 PM | | PASS |
|
|
No changes since prior inspection. Interior work is in progress.
|
ESC13-00230
| Conference | 10/31/2013 | 10/31/2013 | 10/31/2013 3:16:40 PM | P | DONE |
|
|
Telephone conference with RP Jay Walker and Brighton inspector Daniel. Discussed the following: 1. Landscapers, fence builders, and others are currently causing track out due to not using construction entrances.
2. Due to subdivision grading process, initial entrances have been removed at this time.
3. All grading will be finished by 1st week of November
4. Street cleanup once grading has been completed. 5. Hydroseeding will occur within 14 days for stabilization.
|
ESC12-00677
| Random Inspection | 10/31/2013 | 10/31/2013 | 10/31/2013 3:04:15 PM | P | PART |
|
|
Cement washout access is muddy and resulting in track out. Talked to Hunter Homes RP Rollo Bird and requested that more rock material (construction entrance) be placed around washout. The washout is actually in Timberside phase 2. Will reinspect when back in area.
|
ESC13-00584
| General Inspection | 10/31/2013 | 10/31/2013 | 10/31/2013 2:43:25 PM | | PASS |
|
|
Construction entrance was provided since last inspection. No violations at this time. WIP.
|
ESC11-00732
| General Inspection | 10/31/2013 | 10/31/2013 | 10/31/2013 2:42:52 PM | | PASS |
|
|
No construction activity. Greenbelt has been realigned and vegetation is stabilizing banks. May want to close out permit.
|
ESC13-00570
| General Inspection | 10/31/2013 | 10/31/2013 | 10/31/2013 2:41:15 PM | | PASS |
|
|
WIP. No corrections at this time.
|
ESC13-00983
| Site Preparation | 10/31/2013 | 10/31/2013 | 10/31/2013 2:40:52 PM | P | PART |
|
|
Braxton Phone #: ###-#### Site prep called in by RP. Work had already begun prior to inspection, issued warning that Site prep inspections should occur prior to excavation. Permit was posted, and perimeter wattle was installed. No construction entrance. Told excavator to sweep up track out from his operations.
|
ESC13-01017
| Site Preparation | 10/31/2013 | 10/31/2013 | 10/31/2013 2:38:42 PM | P | PASS |
|
|
Rollo Phone #: ###-####
Permit posted. Silt fence provided on down slope, wattle/Gator Guard protecting east side of lot and back-filled. Called RP Rollo and requested that Gatorguard be staked down, upon which he agreed.
|
ESC13-00395
| Aging Inspection | 10/31/2013 | 10/31/2013 | 10/31/2013 12:37:09 PM | | CANC |
|
|
|
ESC13-00270
| Aging Inspection | 10/31/2013 | 10/31/2013 | 10/31/2013 12:37:00 PM | | CANC |
|
|
|
ESC13-00390
| Aging Inspection | 10/31/2013 | 10/31/2013 | 10/31/2013 12:36:52 PM | | CANC |
|
|
|
ESC13-01079
| Conference | 10/31/2013 | 10/31/2013 | 10/31/2013 11:02:37 AM | P | PASS |
|
|
Met with Shayne Geib, Operations Manager at Cutting Edge to discuss scope of project along Whitewater Blvd.
Operations: 1. Screen existing stockpile onsite (per consent with Alta) 2. Place screened topsoil material in tree holes and compact . This will be done using front end loader and dump truck 3. An auxilliary stockpile will be at corner of Fairview and Whitewater for work at that end of project.
BMPs: 1. Provided construction entrance at round about where screening operation is occuring 2. Manual sweeping of any dirt on sidewalks/street 3. Level tree hole topsoil piles below curbing.
Questions call Shayne ###-####
|