BLD99-01896
| BLD-Wall cover | 10/1/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | | PASS |
|
|
Scheduled by a contractor via Hello! on 10/01/1999 at 14:00:16. Contact: ###-####.
|
BLD99-01666
| BLD-Framing/Rough-in | 10/1/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | A | FAIL |
|
|
Ken ###-#### truss needs repairs for spit cords, also front porch truss require bearing
|
BLD99-02521
| BLD-Footing | 10/1/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | A | FAIL |
|
|
###-####--SHELBY ---FT RE-INSP prior to correction of compaction report needed , also rebar required throught out by approved plans, not done.
|
BLD99-02834
| BLD-Foundation | 10/1/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | A | PASS |
|
|
ready at 11:30 Chris ###-####
|
BLD99-02684
| BLD-Framing/Rough-in | 10/1/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 10/01/1999 at 15:39:21. Contact: ###-####. Not ready
|
BLD99-02009
| BLD-Foundation | 9/30/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 09/30/1999 at 14:50:27. Contact: . Subject to special inspection
|
BLD99-01673
| BLD-Footing | 10/1/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 10/01/1999 at 05:54:56. Contact: ###-####. No approved plans left corrections posted at upper portion of footing
|
BLD99-02731
| BLD-Footing | 10/1/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | A | PASS |
|
|
LOGAN-- ###-#### FT INSP appears ok
|
BLD99-01689
| BLD-Final | 10/1/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | A | FAIL |
|
|
CARL ###-####//301 AREA, TOOK FOR RUSS, NEED 1 HR. LISTING ON MED. GAS ROOM DOOR, BRACE COMPRESSOR PLATFORM, NEED FIRE OK. RECALL
|
BLD99-02528
| BLD-Framing/Rough-in | 10/1/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | A | PART |
|
|
Dwayne ###-####//301 AREA, NEED ALL PLAN NOTES, BRACE PARTITIONS, SEAL DEMISING WALL, DAMPER AT DEMISING?? OK TO COVER OFFICE WALLS.
|
BLD99-02920
| BLD-Footing | 10/1/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | A | PASS |
|
|
Dean ###-####
|
BLD98-03090
| BLD-Framing/Rough-in | 10/1/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | A | PASS |
|
|
bill ###-#### ok as no electrical in at this time, said none was going in
|
BLD99-01809
| BLD-Framing/Rough-in | 10/1/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | P | PART |
|
|
ceiling inspection Richard ###-#### area at left front, not done, verify at final
|
BLD98-03345
| BLD-Wall cover | 10/1/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | P | FAIL |
|
|
Sceduled by a contractor via Hello! on 10/01/1999 at 16:45:03. Contact: ###-####. Engineering on plan not clear, engineer to field verify
|
BLD97-00878
| BLD-Framing/Rough-in | 10/4/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | P | PASS |
|
|
chris ###-#### fr insp--call when at site energy code only, framing already approved
|
BLD99-02680
| BLD-Footing | 10/4/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 10/04/1999 at 09:25:38. Contact: ###-####.
|
BLD99-02526
| BLD-Foundation | 10/4/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | P | PASS |
|
|
WES-- ###-#### STEM WALL INSP
|
MEC99-03159
| Rough-in | 10/4/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | P | PASS |
|
|
contractor will fix pipe under house by final Lars ###-#### call first if any questions dryer vent ok
|
BLD99-02967
| BLD-Footing | 10/4/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | P | NR |
|
|
John ###-####
|
BLD98-01168
| BLD-Conference | 10/4/1999 | 10/4/1999 | 10/4/1999 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 10/04/1999 at 10:27:40. Contact: ###-####. Ok to install ceiling grid in portion of 4th floor
|