Inspections for the day of: Wednesday, October 4, 2000.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Storey
TitleBLD-COM/RES INSPECTOR
Phone #794-9490
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD00-02375 BLD-Concrete10/3/200010/4/200010/4/2000 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 10/03/2000 at 13:50:01. Contact: ###-####. sub basement ft and rebar ok for placement. north/east exterior wall lines. pending mti special inspection report. 10/4/2000 9:34:22 AM
BLD98-01409 BLD-Conference10/3/200010/4/200010/4/2000 12:00:00 AMAPART
Wants Jim Story to take the inspection per George Slane Mike Mason ###-#### pending resubmital from arch. to address 2 hr. assembly. 10/4/2000 1:37:25 PM
BLD99-02805 BLD-Energy code compliance10/4/200010/4/200010/4/2000 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 10/04/2000 at 07:40:26. Contact: ###-####. ok for cover. 10/4/2000 2:04:15 PM
MEC00-03371 Pressure Test10/4/200010/4/200010/4/2000 12:00:00 AMPPASS
pres test-- randy ###-#### cell cert. by gas co. 10/4/2000 9:55:20 AM
BLD00-02328 BLD-Final10/3/200010/4/200010/4/2000 12:00:00 AMPPASS
keith ###-#### l/c ok. 10/4/2000 4:30:09 PM
BLD00-01563 BLD-Concrete10/2/200010/4/200010/4/2000 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 10/02/2000 at 07:04:02. Contact: ###-####. placed w/special insp. pending report. 10/4/2000 1:38:05 PM